Permanent Occupancy | | 12/21/1999 | 12/21/1999 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 12/21/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #8060 issued 12-21-99 to I.A.C.I. on the 2nd floor.
|
FIRE-Final Inspection | 12/6/1999 | 12/7/1999 | 12/7/1999 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/06/1999 at 15:29:27. Contact: ###-####. Occupancy approved.
|
BLD-Final | 12/7/1999 | 12/7/1999 | 12/7/1999 | P | PART |
|
|
|
Ok for temp. oc. w/fire insp. approval until double swing doors are installed.
|
Temporary occupancy | | | 12/7/1999 | | PART |
|
|
|
Temp. Occ. Cert. #3952 issued 12-7-99 to I.A.C.I.
|
FIRE-Final Inspection | 11/18/1999 | 11/19/1999 | 11/19/1999 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/18/1999 at 12:35:50. Contact: ###-####. Exit doors; occupant load sign; panic hardware.
|
BLD-Final | 11/18/1999 | 11/19/1999 | 11/19/1999 | P | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 11/18/1999 at 12:36:42. Contact: ###-####. Fire fail/ no fire sign-off.
|
BLD-Framing/Rough-in | 11/8/1999 | 11/9/1999 | 11/9/1999 | A | PASS |
|
|
|
Scheduled by a contractor via Hello! on 11/08/1999 at 11:46:37. Contact: ###-####. Ok to cover walls.
|
Print Occupancy Form | | | 11/8/1999 | | DONE |
|
|
|
was given wrong occ card issued duplicate.mps
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/1999 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 11/3/1999 | | DONE |
|
|
|
|
Telephone call | | | 11/3/1999 | | DONE |
|
|
|
called Wess at ###-####left message and I also called Gary Christenson ###-#### and left a message
|
Issue PAID IN FULL permit | | | 11/3/1999 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/28/1999 | | 11/3/1999 | | PASS |
Carl Westfall
|
|
|
11/3/99 08:28:03 CJW - activity updated through activity BLDA022 from case BLD99-02826.
|
Routing - PLAN CHECK | 11/2/1999 | | 11/3/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 11/2/1999 | | PASS |
|
|
|
Drawings approved, with conditions, after resubmittal review.
|
Routing - FIRE | 10/26/1999 | | 11/1/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 11/1/1999 | | PEND |
|
|
|
|
Plan resubmittals received | | | 10/29/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM PATRICK McKEEGAN, FORWARDED SAME TO CARL WESTFALL. 10/29/99 DAR
|
Routing - PLAN CHECK | 9/29/1999 | | 10/26/1999 | | |
|
|
|
|
Plan Reviewer's activity | | | 10/22/1999 | | PEND |
|
|
|
UBC plan review started October 21, 1999 and finished October 26, 1999. A response from the architect is required. See the conditions list.
|
Routing - PUBLIC WORKS | 9/29/1999 | | 9/29/1999 | | PASS |
|
|
|
|
Pending Assignment by MYS | 9/20/1999 | | 9/28/1999 | | DONE |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 9/28/1999 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Received Certificate of Value | | | 9/21/1999 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/21/1999 | | PEND |
|
|
|
PLANS ARE NOT FULLY DIMENSIONED WITH ROOM USAGE BEING CALLED OUT. KMM
|
Fee Review-notes | 9/20/1999 | 9/20/1999 | 9/20/1999 | | DONE |
|
|
|
|
Application received | | | 9/20/1999 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/20/1999 | | DONE |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|