Fee Review-notes | 6/16/2003 | 6/16/2003 | 6/16/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 12/29/1999 | 12/29/1999 | | DONE |
|
|
|
|
BLD-Final | 12/28/1999 | 12/29/1999 | 12/29/1999 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/28/1999 at 16:26:37. Contact: ###-####. Card left on site.
|
Permanent occupancy | | | 12/29/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #8066 issued 12-29-99 to the Pony Express.
|
FIRE-Final Inspection | 12/27/1999 | 12/28/1999 | 12/28/1999 | P | NR |
Rick Jackson
|
|
|
JC ###-#### REINSPECTION.
|
FIRE-Final Inspection | 12/22/1999 | 12/23/1999 | 12/23/1999 | P | FAIL |
Rick Jackson
|
|
|
JC ###-#### FIRE FN. Exit signs.
|
FIRE-Sprinkler Rough-in | 12/22/1999 | 12/23/1999 | 12/23/1999 | P | PASS |
Rick Jackson
|
|
|
JC -- FIRE LIFE SAFETY --###-####. Sprinklers ok in tenent space.
|
BLD-Other | 12/21/1999 | 12/22/1999 | 12/22/1999 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/21/1999 at 16:03:30. Contact: ###-####. Light wires & spreader bar's must be installed ok to drop tile- Ck from mech. Access.
|
BLD-Framing/Rough-in | 11/24/1999 | 11/24/1999 | 11/24/1999 | P | PASS |
Jim Storey
|
|
|
jc ###-#### plumb. Pend. Insp.
|
Issue PAID IN FULL permit | | | 11/22/1999 | | DONE |
|
|
|
|
Routing - FIRE | 11/17/1999 | 11/18/1999 | 11/19/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/18/1999 | 11/18/1999 | 11/19/1999 | | PASS |
|
|
|
Plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/19/1999 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/19/1999 | | |
|
|
|
|
Case Summary (BLD) | | | 11/19/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/19/1999 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/19/1999 | | DONE |
|
|
|
|
Telephone call | | | 11/19/1999 | | DONE |
|
|
|
called and left a message for Tim Harris 1-###-####
|
Plan assigned to (JCB) | 10/19/1999 | | 11/19/1999 | | PASS |
Jason Blais
|
|
|
|
Plan Review Completed(1st rev) | | | 11/18/1999 | | PEND |
|
|
|
|
Plan resubmittals received | | | 11/17/1999 | | PEND |
|
|
|
Received plan resubmittals from Larson Architects, forwarded same to Jason Blais. 11/18/99 DAR
|
Routing - PLAN CHECK | 10/21/1999 | | 11/16/1999 | | FAIL |
|
|
|
Plan review report sent and faxed to architect. Written response and some clarifications needed for quick review. Plans routed to fire dept.
|
Plan resubmittals requested | | | 11/16/1999 | | PEND |
|
|
|
Written response and clarifications needed.
|
Case Summary (BLD) | | | 11/16/1999 | | |
|
|
|
|
Routing - PUBLIC WORKS | 10/19/1999 | | 10/21/1999 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 10/19/1999 | | DONE |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 10/18/1999 | | PASS |
|
|
|
|
Received Certificate of Value | | | 10/18/1999 | | |
|
|
|
|
Fee Review-notes | 10/15/1999 | 10/15/1999 | 10/15/1999 | | DONE |
|
|
|
|
Application received | | | 10/15/1999 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/15/1999 | | DONE |
|
|
|
|