Final | 5/17/2019 | 5/17/2019 | 5/17/2019 | P | PASS |
Mark Moncarr
|
|
|
Harold Phone #: ###-#### Ok final floor heat downstairs.
|
Electrical Rough-In | 10/18/2018 | 10/18/2018 | 10/18/2018 | P | PASS |
Mark Moncarr
|
|
|
Harold Phone #: ###-#### Ok cover areas needed to route new floor heat power. Wall under thermo, understairs, and in hallway to E end of basement.
|
Electrical Rough-In | 8/2/2018 | 8/3/2018 | 8/3/2018 | A | PASS |
Mark Moncarr
|
|
|
Harold Phone #: ###-#### Ok cover floor heat downstairs.
|
Conference | 7/26/2018 | 7/27/2018 | 7/27/2018 | A | DONE |
Mark Moncarr
|
|
|
Harold Phone #: ###-#### Discussed the installation of Danfoss floor heat in down bed. Follow manu specs, and complete a load calculation upon RI inspection.
|
Final | 7/25/2018 | 7/27/2018 | 7/27/2018 | A | CANC |
Mark Moncarr
|
|
|
Harold Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/25/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 7/25/2018 | | DONE |
|
|
|
This permit was created on the web by Harold Wright
|