Site Final | 6/28/2006 | 6/28/2006 | 6/28/2006 | P | PASS |
Aimee Hughes
|
|
|
Final stabilization has been completed.
|
Complaint Inspection | 1/26/2006 | 1/26/2006 | 1/26/2006 | P | PART |
Aimee Hughes
|
|
|
Responded to citizen complaint regarding mud and dirt trackout onto the street. I spoke with the RP and informed him that one correction notice would be given regarding mud and dirt trackout due to the number of violations last winter and then a Stop Work would be issued; however the site did not warrant a c/n today. Notified complaintant that I had visited the site.
|
Tracking Control | 11/2/2005 | 11/16/2005 | 11/18/2005 | A | PASS |
Aimee Hughes
|
|
|
Site looks okay. bmp's have been installed.
|
BMP Violation | 11/2/2005 | 11/2/2005 | 11/2/2005 | P | FAIL |
Aimee Hughes
|
|
|
c/n issued for heavy trackout on streets and sidewalks and improper installation of bmp's. contacted RP.
|
Random Inspection | 7/22/2005 | 7/22/2005 | 7/22/2005 | P | PASS |
Aimee Hughes
|
|
|
contacted RP about getting ESC sign posted.
|
Issue & PRINT permit SFD | | | 7/6/2005 | | DONE |
|
|
|
|
Issue & PRINT permit SFD | | | 6/17/2005 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 5/27/2005 | | 5/27/2005 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Application received | | | 5/19/2005 | | |
|
|
|
|