Site Final | 7/9/2007 | 7/9/2007 | 7/9/2007 | P | PASS |
Aimee Hughes
|
|
|
Final stabilization has been completed.
|
Tracking Control | 1/16/2007 | 1/16/2007 | 1/16/2007 | A | PART |
Aimee Hughes
|
|
|
site looks better, some of the track out has been addressed and will contiune to be cleaned up as the ground thaws. Informed RP that site is still not up to MEP...efforts are being made to get all sites into compliance and I will reinspect sites again.
|
BMP Violation | 1/3/2007 | 1/4/2007 | 1/4/2007 | A | PASS |
Aimee Hughes
|
|
|
Site looks okay.,
|
BMP Violation | 12/26/2006 | 12/26/2006 | 12/26/2006 | P | FAIL |
Aimee Hughes
|
|
|
c/n issued to builder for all houses in subdivision addressing trash on sites, mud and dirt track out, and posting ESC signs. all bmp's must be maintained and inspected regularly. notifying all builders and RP's in subdivision.
|
Issue & PRINT permit SFD | | | 10/19/2006 | | |
|
|
|
|
Routing - Erosion and Sediment | 10/17/2006 | | 10/17/2006 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Application received | | | 10/10/2006 | | |
|
|
|
|