Site Final | 7/31/2009 | 7/31/2009 | 7/31/2009 | A | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 7/31/2009 | 7/31/2009 | 7/31/2009 | P | PASS |
Mike Jordan
|
|
|
Final stabalization has been completed.
|
General Inspection | 5/18/2009 | 5/19/2009 | 5/20/2009 | A | FAIL |
Jim Sly
|
|
|
Re-install protection at all drain inlets....sweep all hard surfaces
|
General Inspection | 5/18/2009 | 5/18/2009 | 5/18/2009 | P | CANC |
Jim Sly
|
|
|
Re-sched.....
|
General Inspection | 5/7/2009 | 5/11/2009 | 5/11/2009 | A | PASS |
Clint A Smith
|
|
|
|
Site Preparation | 5/7/2009 | 5/7/2009 | 5/7/2009 | P | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Clean up sediment built up surrounding both D.I. Will re-inspect on 5/11/09AM
|
BMP Violation | 5/5/2009 | 5/6/2009 | 5/6/2009 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 5/5/2009 | 5/5/2009 | 5/5/2009 | P | FAIL |
Eric Strole
|
|
|
left verbal correction with rp to put trash in a container or remove from site, clean & maintain di boxes, install wattles around concrete & asphalt piled in parking lot & clean dirt & debris off all hard surfaces. will reinspect 5-6-09 pm.
|
Tracking Control | 4/21/2009 | 4/23/2009 | 4/23/2009 | A | PASS |
Clint A Smith
|
|
|
|
Random Inspection | 4/21/2009 | 4/21/2009 | 4/21/2009 | P | FAIL |
Clint A Smith
|
|
|
Message with RP: CLean up all hard surfaces by 4/22/09 PM Will re-inspect on 4/23/09AM
|
BMP Violation | 3/26/2009 | 3/27/2009 | 3/27/2009 | P | PART |
Clint A Smith
|
|
|
In the process of cleaning up the project. All signs have been placed.
|
Site Preparation | 3/26/2009 | 3/26/2009 | 3/26/2009 | | PART |
Clint A Smith
|
|
|
Verbal to RP: 2. Post "ESC" sign (Vertical Construction) next to there other ESC sign, and also there "Concrete Washout" sign at the washout that they have provided. 2. Re-place there sand bag that is broken open that they are using as external protection for there D.I. within there project area. Will re-inspect on 2/27/09PM.
|
Site Preparation | 3/20/2009 | 3/20/2009 | 3/20/2009 | P | PASS |
Jim Sly
|
|
|
Jim White
|
Issue & PRINT permit COM | | | 3/19/2009 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 2/20/2009 | | 2/20/2009 | | PASS |
Steven Webb
|
|
|
ESC plan approved with attached conditions.
|
Application received | | | 2/13/2009 | | |
|
|
|
|