INSP-Final Inspection | 10/11/2002 | 10/11/2002 | 10/11/2002 | A | PASS |
Troy Cobbley
|
|
|
fire alarm finaled
|
DOC - Permit Finaled | 10/11/2002 | 10/11/2002 | 10/11/2002 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 10/11/2002 11:13:54 AM
|
INSP-Final Inspection | 10/8/2002 | 10/10/2002 | 10/10/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide an updated one line with the correct zone numbers for the fire inspector and provide the same for a building map 10/10/2002 10:47:12 AM
|
CHANGE STATUS TO (ISS) | | | 10/8/2002 | | DONE |
|
|
|
resubmittal changed status
|
Alarm Plan Check | 9/30/2002 | | 10/4/2002 | | PASS |
|
|
|
Resubmittal made after 1st inspection of installation, to reflect the actual horn strobes installed; new cut sheets and battery calculations included. No other changes to plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/4/2002 | | DONE |
|
|
|
A $100 fee applies for this additional review -10/4/2002.
|
Inspection Record Card- Fire | 10/4/2002 | | 10/4/2002 | | DONE |
|
|
|
|
Telephone call | | | 10/4/2002 | | DONE |
|
|
|
resub ready and fees due
|
Application received | | | 9/30/2002 | | DONE |
|
|
|
resubmittal received for previously issued plans.
|
INSP-Final Inspection | 9/23/2002 | 9/24/2002 | 9/24/2002 | P | FAIL |
Troy Cobbley
|
|
|
strobe overspaced in n.e. corner of building #4, provide weatherproof listing for the A/V installed on the exterior wall, provide revised battery calculations for the a/v's since what is installed is not what was submitted, wire the circuits to match the plans submitted, clean up the wiring in the fire alarm panel, the inspection was stopped due to the problems listed above 9/24/2002 2:31:26 PM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2002 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/11/2002 | | 7/11/2002 | | DONE |
|
|
|
|
Telephone call | | | 7/11/2002 | | DONE |
|
|
|
PERMIT READY AND FEES DUE
|
Issue and Print Permit | | | 7/11/2002 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 4/15/2002 | | 7/11/2002 | | DONE |
|
|
|
7/11/2002 15:08:37 SLR - activity updated through activity FIRA22 from case FIR02-00151.
|
Alarm Plan Check | | | 7/11/2002 | | PASS |
|
|
|
7/11/02 Alan at Alarmco called with necessary information.
|
Telephone call | | | 7/11/2002 | | DONE |
|
|
|
Alarm at Alarmco called; provided additional information on multiplex design, and ceiling shape in gymnasiums to confirm detector placement. Can now complete plan review.
|
Alarm Plan Check | | | 7/10/2002 | | HOLD |
|
|
|
Additional information required. Awaiting call from Alarmco to discuss.
|
Meeting | | | 6/27/2002 | | DONE |
|
|
|
1 hour meeting with Alan Manor, Alarmco to discuss the 6/17/resubmittal which still did not include the information specifically requested in the original review comments. The 2nd set of plans returned to him for revision.
|
Alarm Plan Check | 6/17/2002 | | 6/27/2002 | | FAIL |
|
|
|
Resubmittal did not include information specifically required in original reivew comments. No further review done. One set of plans returned to Alarmco for revision.
|
Miscellaneous action | | | 5/9/2002 | | DONE |
|
|
|
one set of plans returned to Alarmco for revision.
|
Alarm Plan Check | | | 5/2/2002 | | FAIL |
|
|
|
Review faxed to Alarmco. Plans inadequate for a full review.
|
Application received | | | 4/15/2002 | | |
|
|
|
|