INSP-Final Inspection | 11/25/2002 | 11/25/2002 | 11/25/2002 | P | PASS |
Troy Cobbley
|
|
|
|
DOC - Permit Finaled | 11/25/2002 | 11/25/2002 | 11/25/2002 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 11/25/2002 3:18:01 PM
|
INSP-Final Inspection | 11/14/2002 | 11/15/2002 | 11/15/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide clevis hangers on both sides of where the 1" armovers attach to the branchline. I spoke to greg with treasure valley fire about this 11/15/2002 2:47:19 PM
|
INSP-Sprinkler Rough-in | 10/29/2002 | 10/29/2002 | 10/29/2002 | P | FAIL |
Troy Cobbley
|
|
|
sprinkler heads in the soffit are incorrectly hung from the soffit bracing, existing sprinkler hangers must be installed to the top of the trusses with retaining straps, the earth quake bracing is to be attached to the top of the truss as well 10/29/2002 3:57:08 PM
|
Issue and Print Permit | | | 10/25/2002 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/24/2002 | | 10/24/2002 | | DONE |
|
|
|
|
Telephone call | | | 10/24/2002 | | DONE |
|
|
|
permit ready and fees due
|
Plan assigned to (Bill) | 10/22/2002 | | 10/24/2002 | | DONE |
|
|
|
10/24/2002 14:03:26 JWA - activity updated through activity FIRA22 from case FIR02-00417.
|
Sprinkler Plan Check | 10/22/2002 | | 10/24/2002 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/2002 | | DONE |
Bill Alexander
|
|
|
|
Application received | | | 10/22/2002 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|