Information based on query as of Saturday, September 28, 2024.
Permit Information
Permit NumberFIR04-00584
StatusFinaled
Name MICRON TECHNOLOGY INC FP
Site Address 8000 S FEDERAL WAY
Project NameSPR MICRON 24 WAFER & QUARTZ
Customer Number7362
ePlanReview 
Description
MICRON BUILDING #24 - FC REMODEL FOR CENTRAL TEST WAFER AND QUARTZ CLEAN (#7362) To demo fire sprinklers for the removal of some interior partitions and suspended ceilings and reinstall fire sprinklers for new cleanroom walls, and HEPA ceiling system for the creation of 550-ft/2 Quartz Clean Bay (109B) and a 980-ft/2 Quartz Clean Backend (109C). This work is being done in an approximate 1530 square foot area of the north end of the first floor of Building #24, between grid lines #G & #H and #2 & #5. This fire protection work shall comply with the IFC 2000 and the permit review comments; each regulated by the Fire Chief. The review comments, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD04-02270.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/2/20052/3/20052/3/2005PPASS
DetailsRick Jackson
Cell Ph. ###-####; Phone #: ###-#### Internet Inspection Request from: Daniel Buccino
DOC - Permit Finaled2/3/20052/3/20052/3/2005PPASS
DetailsRick Jackson
Finaled by inspector at 2/3/2005 4:15:47 PM
INSP-Sprinkler Rough-in/Hydro12/14/200412/15/200412/15/2004APART
DetailsRick Jackson
Cell Phone ###-####; Phone #: ###-#### Internet Inspection Request from: Daniel Buccino Subfloor okay to cover 12/15/2004 8:59:00 AM
INSP-Sprinkler Rough-in/Hydro12/14/200412/14/200412/14/2004PNR
DetailsRick Jackson
Cell Ph. ###-####. Rick, this is a partial. We are finished with the underfloor.; Phone #: ###-#### Internet Inspection Request from: Daniel Buccino Dan called and said he would reschedule as the approved plans can't be located 12/14/2004 12:41:17 PM
Issue and Print Permit  11/4/2004 DONE
Plan assigned to (Bill)9/22/2004 11/3/2004 DONE
Sprinkler Plan Check9/27/2004 11/3/2004 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  11/3/2004 DONE
Permit Ready to Issue  11/3/2004 DONE
Inspection Record Card- Fire11/3/2004 11/3/2004 DONE
Telephone call  11/3/2004 DONE
E-mailed Paul & Max that permit is ready & fees///11/03/04 4:35pm BAS
Miscellaneous action  9/30/2004 DONE
Per telcon with Paul Marcolina agreed to allow srpinkler heads to be removed below the hepa filter ceiling which is to be demolished prior to issuing this permit, on the understanding that acceptable sprinklers are in service beneath the machine deck above the space which is to be demo'd.
Plan resubmittals received  9/30/2004  
Faxed to ###-####-Not recorded by permit desk.
Miscellaneous action  9/27/2004 DONE
Sent Paul Marcolina an email addressing that this permit will require plan submittals and some more details, not addressed.
Application received  9/22/2004