INSP-Final Inspection | 8/20/2007 | 8/21/2007 | 8/21/2007 | A | PASS |
Forrest France
|
|
|
Correction items are complete, fire sprinkler permit finaled.
|
INSP-Final Inspection | 8/16/2007 | 8/17/2007 | 8/17/2007 | A | FAIL |
Forrest France
|
|
|
Need to fire stop locations where the new main and hose valve piping pass through the riser room walls to maintain the 1hr. rating, missing hangers at one piece of new 4" main, the flow switch has been left mechanicaly disabled and needs to be put back into service immediately-notified contractor this is to be done ASAP.
|
INSP-Final Inspection | 8/15/2007 | 8/16/2007 | 8/16/2007 | A | CANC |
Forrest France
|
|
|
Overbooked, no time available for this inspection today.
|
INSP-Sprinkler Rough-in | 8/15/2007 | 8/16/2007 | 8/16/2007 | A | CANC |
Forrest France
|
|
|
Overbooked, no time available for this inspection today.
|
Issue and Print Permit | | | 8/3/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/1/2007 | | 8/1/2007 | | DONE |
|
|
|
|
Telephone call | | | 8/1/2007 | | DONE |
|
|
|
left vm for lillie scales at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 8/1/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/11/2007 | | 7/30/2007 | | PASS |
|
|
|
plans are approved as submitted by Bryan Johnson
|
Plan resubmittals received | | | 7/23/2007 | | |
|
|
|
|
Application received | | | 7/11/2007 | | |
|
|
|
plans originally submitted on 6/29/07 under the wrong permit # as a resubmittal for Fir07-00234. This permit should have been created instead.
|
Pending Assignment by SAM | 7/11/2007 | | | | |
|
|
|
|