INSP-Final Inspection | 8/27/2007 | 8/28/2007 | 8/27/2007 | P | PASS |
Forrest France
|
|
|
Final fire sprinkler inspection passed, permit finaled.
|
INSP-Final Inspection | 8/16/2007 | 8/17/2007 | 8/17/2007 | P | PART |
Forrest France
|
|
|
Necessary corrections have been made, OH install is approved for cover at the drop ceilings, final pending ceiling tile and escutcheons.
|
INSP-Sprinkler Rough-in/Hydro | 8/15/2007 | 8/16/2007 | 8/16/2007 | A | FAIL |
Forrest France
|
|
|
Heads at several locations including along the west wall of the sales floor exceed maximum allowed spacing for OH group 2 as designed. The hydrostatic test passed.
|
Issue and Print Permit | | | 8/15/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/14/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/14/2007 | | 8/14/2007 | | DONE |
|
|
|
|
Telephone call | | | 8/14/2007 | | |
|
|
|
tlk to rick reynolds ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 8/14/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/25/2007 | | 8/13/2007 | | PASS |
|
|
|
Plans are approved as submitted by Bryan Johnson
|
Telephone call | | | 8/10/2007 | | DONE |
|
|
|
telcon from Carrie, CSDI re status of reviw. Should be done by Monday. Suggested she ask contractor to send in an Early Start Request, which would allow them to start immediately.
|
Miscellaneous action | | | 8/10/2007 | | DONE |
|
|
|
Approved Early Start request to begin installation work per submitted plans. Copy attached.
|
Application received | | | 7/25/2007 | | |
|
|
|
|
Case Summary | | | 7/25/2007 | | DONE |
|
|
|
|
Pending Assignment by SAM | 7/25/2007 | | | | |
|
|
|
|