Information based on query as of Friday, September 27, 2024.
Permit Information
Permit NumberFIR07-00812
StatusFinaled
Name AMERICAN FIRE PROTECTION LLC
Site Address 251 W GOWEN RD
Project NameWestern Trailers
Customer Number 
ePlanReview 
Description
Scope of Work:
Beginning from an existing 8" gate valve located in the street, run 140'-6" of 8" C-900 out and stub up into the future 55,415-ft/2 type IIB, two story structure. The fire sprinkler underground work shall comply with NFPA 13-2002, NFPA 24-2002 the IFC-2003, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum fire code. This permit is attached to building permit: BLD07-01884.


Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary  10/29/2008 DONE
INSP-Final Inspection7/15/20087/15/20087/15/2008PPASS
DetailsForrest France
Underground permit finaled.KR
INSP-Final Inspection6/20/20086/20/20086/20/2008PPART
DetailsForrest France
UG flush and hydrostatic tests are complete.
INSP-Sprinkler Rough-in/Hydro6/18/20086/18/20086/18/2008PPART
DetailsForrest France
UG fire supply line hydrostatic test passed.
INSP-Sprinkler Rough-in/Hydro5/28/20085/29/20085/30/2008AFAIL
DetailsForrest France
Inspection for the office areas only second and first floors north side completed today, noted SW head at the first floor stair landing is too low, line under the staris at the warehouse is 1 1/4 fed by a 1" tap-also missing ret. strap at a beam clamp, will require as-built plans for the second floor branchline pipe size changes, stairway heads at the 2nd floor are not complete, verified items from previous inspection are done, okayed for cover at the drop ceilings.
INSP-Sprinkler Rough-in/Hydro5/23/20085/27/20085/27/2008PFAIL
DetailsForrest France
Rough-in cover inspection for the office area failed due to decking insulation covering all pipe hanger attatchments-need to expose the work for verification of seismic restraint at the beam clamps-selected one random hanger for inspection and discovered the retaining strap had not been fastened, also missing EQ bracing at the 3" main, noted stairway heads are not cut, need to provide approved plan set.
INSP-Sprinkler Rough-in/Hydro5/13/20085/14/20085/14/2008PPART
DetailsForrest France
UG fire supply line flush completed satisfactory, UG hydrostatic test is not ready at this time due to pressure loss during initial pretest per contractor.
Miscellaneous action  11/8/2007 DONE
Per telcon 11/7/08, John Lee, United Water, confirmed that United Water installed the main to the west of the Western Trailer facility and the two separate taps for hydrant and sprinkler supply to Western Trailers. It is a UW distribution main and is intended to be extended in time to supply the two flag lots behind this parcel.
INSP-Sprinkler Rough-in10/24/200710/25/200710/25/2007APART
DetailsForrest France
UG fire supply line installation per scope of work is acceptable pending satisfactory compliance with Boise City Fire Prevention Code adoption 7-01-46. The fire service line must be dedicated single use for the overhead fire sprinkler system or be looped if accomodating both hydrants and OH supply. Notified contractor of the situation. Per Jim Danes of American Fire the line is planned for future looped connection, date uncertain. Per the civil drawings, the UG fire service line is shown as single use for OH fire protection only.
INSP-Sprinkler Rough-in10/22/200710/23/200710/22/2007ACANC
DetailsForrest France
dan Note: underground inspect for cover Phone #: ###-#### Disp set to [CANC] by a contractor via Hello! on Oct 22 2007 7:57PM.
Issue and Print Permit  10/15/2007 DONE
PLANS/APPL TAKEN TO FRONT DESK  10/11/2007 DONE
Inspection Record Card- Fire10/11/2007 10/11/2007 DONE
Telephone call  10/11/2007 DONE
lft vm with jim danes ###-#### that permit and fees are ready to be picked up
Permit Ready to Issue  10/11/2007 DONE
Sprinkler Plan Check9/27/2007 10/10/2007 PASS
Plans are approved by Bryan Johnson
Application received  9/27/2007  
Pending Assignment by SAM9/27/2007