Case Summary | | | 10/29/2008 | | DONE |
|
|
|
|
INSP-Final Inspection | 7/15/2008 | 7/15/2008 | 7/15/2008 | P | PASS |
Forrest France
|
|
|
Underground permit finaled.KR
|
INSP-Final Inspection | 6/20/2008 | 6/20/2008 | 6/20/2008 | P | PART |
Forrest France
|
|
|
UG flush and hydrostatic tests are complete.
|
INSP-Sprinkler Rough-in/Hydro | 6/18/2008 | 6/18/2008 | 6/18/2008 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/28/2008 | 5/29/2008 | 5/30/2008 | A | FAIL |
Forrest France
|
|
|
Inspection for the office areas only second and first floors north side completed today, noted SW head at the first floor stair landing is too low, line under the staris at the warehouse is 1 1/4 fed by a 1" tap-also missing ret. strap at a beam clamp, will require as-built plans for the second floor branchline pipe size changes, stairway heads at the 2nd floor are not complete, verified items from previous inspection are done, okayed for cover at the drop ceilings.
|
INSP-Sprinkler Rough-in/Hydro | 5/23/2008 | 5/27/2008 | 5/27/2008 | P | FAIL |
Forrest France
|
|
|
Rough-in cover inspection for the office area failed due to decking insulation covering all pipe hanger attatchments-need to expose the work for verification of seismic restraint at the beam clamps-selected one random hanger for inspection and discovered the retaining strap had not been fastened, also missing EQ bracing at the 3" main, noted stairway heads are not cut, need to provide approved plan set.
|
INSP-Sprinkler Rough-in/Hydro | 5/13/2008 | 5/14/2008 | 5/14/2008 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory, UG hydrostatic test is not ready at this time due to pressure loss during initial pretest per contractor.
|
Miscellaneous action | | | 11/8/2007 | | DONE |
|
|
|
Per telcon 11/7/08, John Lee, United Water, confirmed that United Water installed the main to the west of the Western Trailer facility and the two separate taps for hydrant and sprinkler supply to Western Trailers. It is a UW distribution main and is intended to be extended in time to supply the two flag lots behind this parcel.
|
INSP-Sprinkler Rough-in | 10/24/2007 | 10/25/2007 | 10/25/2007 | A | PART |
Forrest France
|
|
|
UG fire supply line installation per scope of work is acceptable pending satisfactory compliance with Boise City Fire Prevention Code adoption 7-01-46. The fire service line must be dedicated single use for the overhead fire sprinkler system or be looped if accomodating both hydrants and OH supply. Notified contractor of the situation. Per Jim Danes of American Fire the line is planned for future looped connection, date uncertain. Per the civil drawings, the UG fire service line is shown as single use for OH fire protection only.
|
INSP-Sprinkler Rough-in | 10/22/2007 | 10/23/2007 | 10/22/2007 | A | CANC |
Forrest France
|
|
|
dan Note: underground inspect for cover Phone #: ###-#### Disp set to [CANC] by a contractor via Hello! on Oct 22 2007 7:57PM.
|
Issue and Print Permit | | | 10/15/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/11/2007 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/11/2007 | | 10/11/2007 | | DONE |
|
|
|
|
Telephone call | | | 10/11/2007 | | DONE |
|
|
|
lft vm with jim danes ###-#### that permit and fees are ready to be picked up
|
Permit Ready to Issue | | | 10/11/2007 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/27/2007 | | 10/10/2007 | | PASS |
|
|
|
Plans are approved by Bryan Johnson
|
Application received | | | 9/27/2007 | | |
|
|
|
|
Pending Assignment by SAM | 9/27/2007 | | | | |
|
|
|
|