INSP-Final Inspection | 7/21/2009 | 7/21/2009 | 7/27/2009 | P | PASS |
Forrest France
|
|
|
Fire alarm finaled.
|
INSP-Final Inspection | 7/17/2009 | 7/21/2009 | 7/21/2009 | A | PART |
Forrest France
|
|
|
Remainder of alarm devices tested okay, final pending repair of loop two ground fault.
|
INSP-Final Inspection | 7/15/2009 | 7/15/2009 | 7/15/2009 | P | CANC |
Troy Cobbley
|
|
|
Please call 30 min prior to arrival. Phone #: ###-#### Internet Inspection Request from: Jeff Walton Inspection cancelled from web by: Jeff Walton
|
INSP-Final Inspection | 2/19/2009 | 2/20/2009 | 2/20/2009 | A | PART |
Forrest France
|
|
|
Fire alarm work completed to date tested satisfactory, additional tool equipment and associated alarm interconnections not yet installed-permit final pending.
|
INSP-Final Inspection | 2/18/2009 | 2/18/2009 | 2/18/2009 | A | CANC |
Forrest France
|
|
|
Please call 30 min prior to arrival. Phone #: ###-#### Internet Inspection Request from: Jeff Walton
|
FIR-Aging Inspection | 1/27/2009 | 1/27/2009 | 1/27/2009 | | DONE |
Forrest France
|
|
|
WIP, pending site inspection request.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/27/2008 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/27/2008 | | DONE |
Rita DeYoung
|
|
|
|
Alarm Plan Check | | | 10/24/2008 | | PASS |
|
|
|
On site plan review. Approved as annotated; subject to fire inspection verification.
|
Plan assigned to (Scott) | | | 10/22/2008 | | DONE |
Sam Rogers
|
|
|
This permit was created on the web by Paul Marcolina
|
Plan assigned to (SAM) | | | 10/22/2008 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|