Miscellaneous action | | | 6/8/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 2/1/2011 | 2/2/2011 | 2/2/2011 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled. Corrections finished.
|
INSP-Final Inspection | 1/27/2011 | 1/28/2011 | 1/28/2011 | A | PART |
Forrest France
|
|
|
Verified previous correction items have been finished, noted system is missing inspectors test connection including valve and test orfice, partition walls at the first floor offices are not yet installed, missing ceiling tile, provide current inspection tags at the riser. Tamper switches at control valves tested okay.
|
INSP-Sprinkler Rough-in | 1/19/2011 | 1/19/2011 | 1/19/2011 | P | DEFR |
Forrest France
|
|
|
Inspection request intended for FIR10-00569 per contractor.
|
INSP-Sprinkler Rough-in | 12/23/2010 | 12/23/2010 | 12/23/2010 | P | PART |
Forrest France
|
|
|
don Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 12/20/2010 | | DONE |
Christina Prado
|
|
|
|
(F) Reprint permit | | | 12/20/2010 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/17/2010 | | 12/17/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 12/17/2010 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/17/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 12/17/2010 | | 12/17/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 12/17/2010 | | DONE |
|
|
|
t/c w don - permit (plan mod) ready and fees given
|
Permit Ready to Issue | | | 12/17/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/15/2010 | | |
|
|
|
recieved 3 copies of application and FP-1 & FP-2
|
INSP-Sprinkler Rough-in/Hydro | 12/8/2010 | 12/8/2010 | 12/8/2010 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed. Overhead rough-in failed due to several issues noted on approved plan set.
|
INSP-Sprinkler Rough-in | 12/6/2010 | 12/6/2010 | 12/6/2010 | P | PART |
Forrest France
|
|
|
Need stamped approved plans on site, discussed hydro testing, soffit obstructions etc.
|
INSP-Sprinkler Rough-in | 11/30/2010 | 11/30/2010 | 12/1/2010 | P | PART |
Forrest France
|
|
|
Overhead okayed for cover at the restroom 1st floor. Upright protection verified at concealed spaces as marked on approved plan set. Discussed spacing issues off adjacent walls with low soffits.
|
Plan assigned to (Tim) | 10/6/2010 | | 10/13/2010 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/13/2010 | | 10/13/2010 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2010 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 10/13/2010 | | 10/13/2010 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 10/13/2010 | | DONE |
|
|
|
t/c w don at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/13/2010 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/13/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/12/2010 | | |
|
|
|
received 3 sets of plans/ applications sent to Tim F for review.
|
Sprinkler Plan Check | 10/8/2010 | | 10/8/2010 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 10/8/2010 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 10/8/2010 | | DONE |
|
|
|
t/c w don at ###-#### - permit denied - needs to be picked up and resubmitted
|
Application received | | | 10/6/2010 | | |
|
|
|
|