Miscellaneous action | | | 7/8/2011 | | DONE |
|
|
|
Plans taken to records for scanning.
|
INSP-Final Inspection | 6/21/2011 | 6/22/2011 | 6/22/2011 | A | PASS |
Forrest France
|
|
|
Fire alarm permit finaled.
|
INSP-Final Inspection | 6/20/2011 | 6/21/2011 | 6/21/2011 | A | PASS |
Forrest France
|
|
|
Modification tested okay, as-builts recieved. Inspection passed.
|
Telephone call | | | 6/14/2011 | | DONE |
|
|
|
Colton with SimplexGrinnell called to ask if as-built drawings would be acceptable for adding a notification device in the pharmacy restroom per the previous inspection comments. After reviewing the originally submitted plans and the case activity, I let him know that as-built drawings would be fine based on the information he gave me of connecting the new device to an existing spare NAC on NAC panel #1 located in Waiting Room 101. I advised him to review the previous inspection comments to ensure all of the items/issues are addressed appropriately and documented on the as-built drawings/documentation.
|
FIR-Aging Inspection | 4/27/2011 | 4/27/2011 | 5/5/2011 | | NR |
Troy Cobbley
|
|
|
I spoke to Tammy with SimplexGrinnell about getting work completed and the inspection finaled. She is following up and will contact me with the project status.
|
INSP-Final Inspection | 2/24/2011 | 2/25/2011 | 2/25/2011 | P | FAIL |
Troy Cobbley
|
|
|
No testing was actually performed. The pull station is required to be relocated as per the approved plans. Not addressed on the plans was the requriement for audibility in the new open office and in the pharmacy. A visual device is required in the new restroom that is located within the pharmacy. Also in the reception area at the pharmacy has what appears to be an existing strobe mounted in a new wall. This device will have to meet current code for spacing or the code under which is was installed if it had not been modified.
|
Issue and Print Permit | | | 11/8/2010 | | |
|
|
|
|
Plan assigned to (Stephanie) | 10/28/2010 | | 11/1/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
|
Plan assigned to (Stephanie) | 10/28/2010 | | 11/1/2010 | | DONE |
Stephanie L. Cobbley
|
|
|
|
1st review completed | | | 11/1/2010 | | DONE |
|
|
|
|
Alarm Plan Check | 11/1/2010 | | 11/1/2010 | | PASS |
Stephanie L. Cobbley
|
|
|
Quick permit approved - no written review comments
|
PLANS TAKEN FRONT DESK ALARM | | | 11/1/2010 | | DONE |
|
|
|
Quick permit approved drawings available at front counter
|
Inspection Record Card- Fire | 11/1/2010 | | 11/1/2010 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 11/1/2010 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 11/1/2010 | | DONE |
Tisha Gallop
|
|
|
called Simplex and told them permit was ready
|
Application received | | | 10/28/2010 | | |
|
|
|
|