Miscellaneous action | | | 6/8/2011 | | DONE |
|
|
|
Sent to records for scanning.
|
INSP-Final Inspection | 5/17/2011 | 5/17/2011 | 5/17/2011 | P | PASS |
Forrest France
|
|
|
Verified resubmital plans, final inspection passed.
|
Override - Parcel Holds | 5/17/2011 | 1/1/1900 | 5/17/2011 | | |
|
|
|
fir inspection
|
CHANGE STATUS TO (ISS) | | | 5/17/2011 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/17/2011 | | DONE |
|
|
|
|
Sprinkler Plan Check | 5/13/2011 | | 5/13/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 5/13/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/13/2011 | | DONE |
Tim Frost
|
|
|
|
Override - Parcel Holds | | | 5/13/2011 | | |
|
|
|
|
Inspection Record Card- Fire | 5/13/2011 | | 5/13/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 5/13/2011 | | DONE |
|
|
|
left vm for ken - permit (plan mod) ready and fees given
|
Override - Parcel Holds | | | 5/13/2011 | | |
|
|
|
|
Permit Ready to Issue | | | 5/13/2011 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/12/2011 | | DONE |
Christina Prado
|
|
|
Received fives sets of application, checklist, technical data sheets, and plans FP1. Routed to Tim Frost for additional review
|
INSP-Final Inspection | 5/9/2011 | 5/9/2011 | 5/9/2011 | P | NR |
Forrest France
|
|
|
Reference plan review comments dated 3/10/11 regarding the need for a plan modification resubmital approval prior to permit final.
|
Override - Parcel Holds | 5/9/2011 | 1/1/1900 | 5/9/2011 | | |
|
|
|
Fir final
|
INSP-Sprinkler Rough-in | 4/18/2011 | 4/18/2011 | 4/18/2011 | P | PART |
Forrest France
|
|
|
Final also pending plan resubmitals per review conditions.
|
INSP-Sprinkler Rough-in/Hydro | 4/4/2011 | 4/4/2011 | 4/4/2011 | P | PART |
Forrest France
|
|
|
Coverage at the storage room and the riser has been added.
|
INSP-Conference | 3/14/2011 | 3/14/2011 | 3/15/2011 | P | DONE |
Forrest France
|
|
|
Regarding existing system.
|
INSP-Sprinkler Rough-in | 3/14/2011 | 3/15/2011 | 3/15/2011 | P | PART |
Forrest France
|
|
|
Overhead modifications per the scope of work okay for cover at the sheetrock ceilings, noted missing coverage at the riser, overspaced pendent head at the storage room, field changes will require plan resubmital to match approved plans with the installation.
|
Sprinkler Plan Check | 3/10/2011 | | 3/10/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 3/10/2011 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/10/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 3/10/2011 | | 3/10/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 3/10/2011 | | DONE |
|
|
|
left vm for ken - permit ready and fees given
|
Telephone call | | | 3/10/2011 | | DONE |
|
|
|
t/c w shaun - permit ready and fees given
|
Permit Ready to Issue | | | 3/10/2011 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/10/2011 | | DONE |
|
|
|
|
Telephone call | | | 3/10/2011 | | DONE |
|
|
|
Jeff Abrshams Alliance Community Radio said he had to have the plans immediately so it would not interfer with their FCC permit. I told him there were errors and the only thing I could do was issue the plan as requiring a Plan Mod which means double fee. He said that was fine. I expedited the plan for them.
Also spoke with John at Allied General in regards to this matte.
|
Application received | | | 3/9/2011 | | |
|
|
|
|
Pending Assignment by SAM | 3/9/2011 | | | | |
|
|
|
|