Miscellaneous action | | | 9/23/2013 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 12/3/2012 | 12/3/2012 | 12/3/2012 | P | PASS |
Forrest France
|
|
|
Permit finaled.
|
INSP-Final Inspection | 11/30/2012 | 11/30/2012 | 11/30/2012 | P | CANC |
Troy Cobbley
|
|
|
Per james and I's discussion this inspection will be rescheduled for monday. Phone #: ###-####
|
INSP-Final Inspection | 11/19/2012 | 11/19/2012 | 11/19/2012 | P | PART |
Forrest France
|
|
|
All modifications to the original design to be shown on as-built drawings including additional heads under ductwork at the dock area. Remainder of revisions are acceptable.
|
INSP-Final Inspection | 10/25/2012 | 10/25/2012 | 10/30/2012 | P | PEND |
Forrest France
|
|
|
Final pending record drawings to match installation and final walkthrough.
|
INSP-Final Inspection | 10/22/2012 | 10/22/2012 | 10/30/2012 | P | PART |
Forrest France
|
|
|
Provide as-built drawings to match field installation including added heads for obstructions and modifications to pipe routing.
|
INSP-Final Inspection | 10/17/2012 | 10/19/2012 | 10/30/2012 | A | PART |
Forrest France
|
|
|
Re-inspection of previous C/N items.
|
CHANGE STATUS TO (ISS) | | | 10/11/2012 | | DONE |
Barbara Stitt
|
|
|
Per Tim Frost
|
Plan assigned to (Tim) | 5/3/2012 | | 5/7/2012 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 5/3/2012 | | DONE |
Christina Prado
|
|
|
Received two sets of plans sheets FP, FP7. One set is "as-builts" the second is "originally approved" Plans given to Tim Frost for further review
|
Plan assigned to (Tim) | 4/20/2012 | | 4/23/2012 | | DONE |
Tim Frost
|
|
|
|
Plan resubmittals received | | | 4/20/2012 | | |
|
|
|
Plan Modification
|
INSP-Sprinkler Rough-in | 4/10/2012 | 4/11/2012 | 4/12/2012 | P | NR |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 4/2/2012 | 4/3/2012 | 4/4/2012 | P | PART |
Forrest France
|
|
|
Inspection items listed 3/30 remain unchanged with the exception of one retainer at the dock and field ceiling tile in place where grid is complete at the non-clean link. Ceilings and sprinkler protection are still lacking at vestibule 100P, closet @ RR 100F, room 100J, column line K, link intersection, and GR100H.
|
INSP-Sprinkler Rough-in/Hydro | 3/30/2012 | 4/2/2012 | 4/2/2012 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/29/2012 | 3/30/2012 | 3/30/2012 | P | NR |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 3/28/2012 | 3/29/2012 | 3/30/2012 | A | FAIL |
Forrest France
|
|
|
Overhead hydrostatic test failed due to visible leakage on the system and pressure loss at the gauge. Re-inspection items noted include; lacking coverage at vestibule 100P- temporary bootie room (missing ceiling and sprinkler heads, outlets are plugged), SW stair 100W exit landing is partially sprinklered, missing field ceiling tile at the TEM labs, leak at non-clean link 100A, construction at the closet adjacent to RR 100F is incomplete, NW stair landing is partially sprinklered, missing ceiling and sprinkler coverage at non-clean link room 100T, missing ceiling tile at non-clean link, heads not installed at column line K temporary wall NE exit, missing head and ceiling at link intersections, secure retainer at dock corridor, noted 5 added uprights not shown on plans below dock area ductwork, plugged outlet and missing ceiling at GR 100H.
|
INSP-Sprinkler Rough-in/Hydro | 3/27/2012 | 3/28/2012 | 3/28/2012 | A | NR |
Forrest France
|
|
|
Need hydrostatic test. Plan modification required for field changes to the approved design including added heads in the calc. area- ref. activity notes dated 2/22/12.
|
INSP-Sprinkler Rough-in/Hydro | 3/2/2012 | 3/2/2012 | 3/2/2012 | P | NR |
Forrest France
|
|
|
Deluge valve installation incomplete at this time. Main and branchline including drops in place. Two drops in need of adjustment.
|
INSP-Sprinkler Rough-in/Hydro | 2/28/2012 | 2/29/2012 | 3/1/2012 | A | PART |
Forrest France
|
|
|
Re-inspection for system 2 corrections finished at the following locations: hall 100R including added seismic bracing, hangers, and spacing okayed with the exception of one area at the intersection of the corridors @ 140ft2: west stair 100W okay for cover: TEM labs 104B thru 104D approved for cover, noted cap at 4" grid main in TEM lab 104E terminates inside a sheetrock wall: auxillary drain at the 4" main relocated to the 6" main at link 100A.
|
INSP-Sprinkler Rough-in/Hydro | 2/20/2012 | 2/21/2012 | 2/22/2012 | P | PART |
Forrest France
|
|
|
Reinspection items at system 2 mechanical include added heads at several locations-6 areas, approx 14 ssu- some in the calc area, rough-in at link 100A okayed, ft2 at corridor 100R not to exceed 130 after pendents are cut in, corrections at nonclean link and TEM labs are incomplete, dock 100C and vestibule 100D no change.
|
INSP-Sprinkler Rough-in | 1/23/2012 | 1/24/2012 | 1/25/2012 | P | FAIL |
Forrest France
|
|
|
Initial rough-in inspection for system # 2 completed and failed due to several issues. General description of such items include and are not limited to; system mains and branch lines at some areas are not installed to design dimentions off walls and columns, 4" main and fittings halfway inside a sheetrock wall, missing crosses for pendent arm-overs at the TEM lab branch pipe, missing coverage below ductwork and other obstructions over 4' throughout the mechanical rooms, incomplete seismic bracing, overspaced coverage at the corridor, added heads at the stair and a new room not reflected on plans, additional storage room adjacent to the loading dock without protection, no access to view installation above the new bootie room, open outlet and missing heads at the end and beginning of the 2 1/2' dirty link branch line- also need to install and secure retainers, etc.
|
Fees Due Hold | 11/4/2011 | | 11/7/2011 | | DONE |
Tisha Gallop
|
|
|
|
Issue and Print Permit | | | 11/3/2011 | | DONE |
Barbara Stitt
|
|
|
|
Sprinkler Plan Check | 11/1/2011 | | 11/1/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/1/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 11/1/2011 | | 11/1/2011 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 11/1/2011 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 11/1/2011 | | DONE |
Barbara Stitt
|
|
|
Left voice message for Karyn that permit is ready for pick up on 11-1-11 @ 2:55pm/BAS
|
Plan resubmittals received | | | 10/24/2011 | | |
|
|
|
10-21-11 received 1 letter of transmittal & 3 plans sent to Tim Frost ///dld
|
Sprinkler Plan Check | 9/22/2011 | | 9/22/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Telephone call | | | 9/22/2011 | | DONE |
|
|
|
left vm for jim - permit denied - needs to be picked up and resubmitted
|
Plan resubmittals received | | | 9/19/2011 | | |
|
|
|
|
Sprinkler Plan Check | 8/25/2011 | | 8/25/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 8/25/2011 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 8/25/2011 | | DONE |
|
|
|
t/c w bob - permit denied - needs to be picked up and resubmitted
|
Miscellaneous action | | | 8/25/2011 | | DONE |
|
|
|
Emailed contractor review
|
Plan assigned to (Tim) | 8/23/2011 | | 8/24/2011 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/23/2011 | | |
|
|
|
|