Miscellaneous action | | | 10/11/2012 | | DONE |
Tim Frost
|
|
|
Sent to Records for scanning.
|
INSP-Final Inspection | 7/5/2012 | 7/5/2012 | 7/6/2012 | P | PASS |
Forrest France
|
|
|
Final walkthrough and inspection completed satisfactory. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 6/22/2012 | 6/22/2012 | 6/22/2012 | P | NR |
Forrest France
|
|
|
Final pending project related fire alarm permit work.
|
INSP-Final Inspection | 6/19/2012 | 6/21/2012 | 6/21/2012 | A | PART |
Forrest France
|
|
|
For inspection items noted 6/18.
|
INSP-Final Inspection | 6/18/2012 | 6/18/2012 | 6/18/2012 | P | CANC |
Troy Cobbley
|
|
|
Jeremy actually wanted a conference/walk through. I found one upright sprinkler head in a second floor room that is blocked by a surface mounted light. Also several pendant heads in the truck bay have ordinary temp heads in locations where intermediate and high temp. heads are required at the unit heaters.
|
Miscellaneous action | | | 4/30/2012 | | DONE |
|
|
|
Tim/Forrest,
Re: FIR11-00483 - 3676 E. Warm Springs Ave.
The building will be maintained above the -10 so the antifreeze will not be an issue for this project. Please consider this email a letter from the owner.
Regards,
Romeo P. Gervais, P.E.
Deputy Chief - Fire Marshal
Boise Fire Department
Ph: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 4/16/2012 | 4/16/2012 | 4/19/2012 | P | PART |
Forrest France
|
|
|
Pendent head relocations at sheetrock ceilings due to fixture obstructions.
|
INSP-Sprinkler Rough-in/Hydro | 4/12/2012 | 4/13/2012 | 4/13/2012 | A | PASS |
Tim Frost
|
|
|
Both systems passed overhead hydro.
|
INSP-Sprinkler Rough-in/Hydro | 3/5/2012 | 3/5/2012 | 3/5/2012 | A | PASS |
Forrest France
|
|
|
Rough-in passed.
|
INSP-Sprinkler Rough-in | 1/19/2012 | 1/19/2012 | 1/24/2012 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 1/23/2012 | 1/23/2012 | 1/23/2012 | A | PART |
Forrest France
|
|
|
Noted correction items finished. Overhead rough-in only passed.
|
INSP-Sprinkler Rough-in | 1/17/2012 | 1/18/2012 | 1/18/2012 | P | PART |
Forrest France
|
|
|
Rough-in inspection completed. Noted items include obstructed upright coverage at the 1st and 2nd floors at some locations due to ductwork, adjacent truss webs, etc. Verified previous c/n items.
|
INSP-Sprinkler Rough-in | 1/17/2012 | 1/17/2012 | 1/18/2012 | P | PART |
Forrest France
|
|
|
C/N items include missing coverage below stairway at the concealed space, obstructed pendent heads at two restrooms, need to provide coverage at combustible concealed spaces or meet allowable exceptions per NFPA 13, plans do not show pendent heads at the equipment bay area.
|
INSP-Conference | 1/17/2012 | 1/17/2012 | 1/17/2012 | A | DONE |
Forrest France
|
|
|
Regarding location of the wall post indicator control valve.
|
Miscellaneous action | | | 1/6/2012 | | DONE |
|
|
|
Reviewed new seismic brace SB-3. It appears to comply with NFPA. Please, see document
|
INSP-Supply line flush | 10/6/2011 | 10/7/2011 | 10/7/2011 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 9/30/2011 | 9/30/2011 | 9/30/2011 | P | PASS |
Forrest France
|
|
|
UG fire supply line hydrostatic testing passed.
|
INSP-Sprinkler Rough-in | 9/27/2011 | 9/27/2011 | 9/28/2011 | P | PASS |
Troy Cobbley
|
|
|
Underground cover inspection passed. Piping can be covered.
|
Issue and Print Permit | | | 9/27/2011 | | DONE |
Barbara Stitt
|
|
|
|
Plan resubmittals received | | | 9/22/2011 | | DONE |
Tisha Gallop
|
|
|
received one copy of application, and three copies of small documents and plans; rourted to fire review
|
Sprinkler Plan Check | 9/22/2011 | | 9/22/2011 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/22/2011 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 9/22/2011 | | 9/22/2011 | | DONE |
Patricia Smith
|
|
|
|
Telephone call | | | 9/22/2011 | | DONE |
|
|
|
left vm for jonathan - permit ready and fees given
|
Permit Ready to Issue | | | 9/22/2011 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 9/7/2011 | | 9/22/2011 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/21/2011 | | 9/21/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
Telephone call | | | 9/21/2011 | | DONE |
|
|
|
t/c w jonathan - permit denied - needs to be picked up and resubmitted
|
Plan resubmittals received | | | 9/16/2011 | | DONE |
Tisha Gallop
|
|
|
received three copies of applcation, small documents and plans; routed to Fire Review.
|
Sprinkler Plan Check | 9/13/2011 | | 9/13/2011 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
There are NO annotations on the plans.
|
1st review completed | | | 9/13/2011 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 9/13/2011 | | DONE |
Tim Frost
|
|
|
Emailed review to contractor
|
Telephone call | | | 9/13/2011 | | DONE |
|
|
|
t/c w jonathan - permit denied - needs to be picked up and resubmitted
|
Application received | | | 9/7/2011 | | |
|
|
|
|
Case Summary | | | 9/7/2011 | | DONE |
|
|
|
|