INSP-Final Inspection | 7/29/2013 | 7/29/2013 | 7/29/2013 | P | PASS |
Forrest France
|
|
|
Fire sprinkler work passed final walkthrough and inspection. Permit finaled.
|
INSP-Final Inspection | 7/25/2013 | 7/26/2013 | 7/26/2013 | A | NR |
Forrest France
|
|
|
Don f. is TVFP site contact ###-#### Phone #: ###-#### >> Inspection requested via web by Brad Bettencourt
|
INSP-Final Inspection | 7/22/2013 | 7/23/2013 | 7/23/2013 | A | PART |
Forrest France
|
|
|
Okay to cover remainder of the drop ceilings in the conference room, ssu relocated. Final pending riser supervision.
|
INSP-Final Inspection | 7/15/2013 | 7/16/2013 | 7/16/2013 | P | PART |
Forrest France
|
|
|
Concluded satisfactory 24 hr. pneumatic test of the new dry system with no pressure loss at the guage. Also finished the remainder of overhead inspection with the exception of the drop ceiling pendents at conf. room 107. Noted one overspaced upright to be relocated.
|
INSP-Sprinkler Rough-in | 7/15/2013 | 7/15/2013 | 7/15/2013 | P | PASS |
Troy Cobbley
|
|
|
24 air test on dry system started at 1:30 with 45psi on the guage
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2013 | 6/28/2013 | 6/28/2013 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic test of the new dry and wet systems passed. Also okayed for cover work at sheetrock ceilings in the bike room, and west entryway.
|
INSP-Sprinkler Rough-in | 6/20/2013 | 6/20/2013 | 6/20/2013 | A | PART |
Forrest France
|
|
|
Ref. stamped plans for locations above hard lids okayed for cover.
|
INSP-Supply line flush | 6/17/2013 | 6/17/2013 | 6/17/2013 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed (post hydrostatic test).
|
INSP-Sprinkler Rough-in | 6/12/2013 | 6/13/2013 | 6/17/2013 | P | PART |
Forrest France
|
|
|
Overhead rough-in at the west and east side restrooms, RR vestibules, and patio areas are approved for cover as marked and dated on stamped plan set.
|
INSP-Sprinkler Rough-in/Hydro | 6/12/2013 | 6/12/2013 | 6/12/2013 | P | PART |
Forrest France
|
|
|
UG fire supply line hydrostatic test completed satisfactory.
|
INSP-Sprinkler Rough-in | 5/29/2013 | 5/29/2013 | 5/29/2013 | A | PART |
Forrest France
|
|
|
UG including the tie-in and 45 ell okay for cover. Overhead work in progress.
|
INSP-Sprinkler Rough-in | 5/22/2013 | 5/22/2013 | 5/22/2013 | P | PART |
Forrest France
|
|
|
UG fire supply line including the IBR and stub out are approved for bury.
|
Sprinkler Plan Check | 4/19/2013 | | 4/19/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/19/2013 | | DONE |
Tim Frost
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/19/2013 | | DONE |
|
|
|
plan mod
|
Plan assigned to (Tim) | 4/18/2013 | | 4/18/2013 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 3/19/2013 | | 3/19/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/19/2013 | | 3/19/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/19/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/2013 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/19/2013 | | |
|
|
|
|
Permit Ready to Issue | | | 3/19/2013 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/19/2013 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/19/2013 | | 3/19/2013 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 3/13/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 13 2013 1:55PM
|