INSP-Final Inspection | 7/25/2013 | 7/26/2013 | 7/29/2013 | P | PASS |
Forrest France
|
|
|
Final walkthrough completed, scope of work finished. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 7/22/2013 | 7/23/2013 | 7/26/2013 | P | NR |
Forrest France
|
|
|
CALL BRAD IN TVFP OFFICE IF ANY QUESTIONS.BARD ###-#### Phone #: ###-#### >> Inspection requested via web by Brad Bettencourt
|
INSP-Final Inspection | 7/22/2013 | 7/22/2013 | 7/22/2013 | P | CANC |
Troy Cobbley
|
|
|
Would like to perform this inspection in conjunction with alarm testing. Please call Brad Bettencourt at the office if there are any issues or questions. Phone #: ###-#### >> Inspection requested via web by Jeff Packham Inspection cancelled from web by: Brad Bettencourt
|
INSP-Final Inspection | 7/15/2013 | 7/16/2013 | 7/16/2013 | A | NR |
Forrest France
|
|
|
|
INSP-Final Inspection | 7/12/2013 | 7/15/2013 | 7/15/2013 | P | CANC |
Troy Cobbley
|
|
|
We would like to schedule this with alarm testing and fire life safety final. Please call with time frame. Phone #: ###-#### >> Inspection requested via web by Jeff Packham Inspection cancelled from web by: Jeff Packham
|
INSP-Final Inspection | 6/28/2013 | 6/28/2013 | 6/28/2013 | P | PART |
Forrest France
|
|
|
Verified added coverage at the tops of both the north and south stairways per plan modification.
|
Issue permit | | | 6/28/2013 | | DONE |
|
|
|
Payment received via Govolutions
|
CHANGE STATUS TO (ISS) | | | 6/28/2013 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 6/27/2013 | | 6/27/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/27/2013 | | 6/27/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2013 | | DONE |
Tim Frost
|
|
|
|
INSP-Sprinkler Rough-in | 6/11/2013 | 6/11/2013 | 6/11/2013 | P | PART |
Forrest France
|
|
|
Sixth floor room 631 as marked on plans is okay for ceiling cover.
|
Plan assigned to (Tim) | 5/30/2013 | | 6/4/2013 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 6/4/2013 | | 6/4/2013 | | PASS |
Tim Frost
|
|
|
Plan Mod #2 - 6/04/2013
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/4/2013 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/4/2013 | | DONE |
Tisha Gallop
|
|
|
|
INSP-Sprinkler Rough-in | 5/20/2013 | 5/21/2013 | 5/21/2013 | P | PART |
Forrest France
|
|
|
ADA rooms north side floors 3,4,5, and 6 okayed for ceiling cover. Rough-in passed.
|
INSP-Sprinkler Rough-in | 5/9/2013 | 5/9/2013 | 5/13/2013 | A | PART |
Forrest France
|
|
|
As-builts for field changes at the first floor lobby soffit and grid ceiling areas recieved. Fire sprinkler work in these areas approved for cover.
|
INSP-Sprinkler Rough-in | 5/8/2013 | 5/8/2013 | 5/13/2013 | P | NR |
Forrest France
|
|
|
|
Permit Ready to Issue | | | 4/19/2013 | | |
|
|
|
|
Inspection Record Card- Fire | 4/19/2013 | | 4/19/2013 | | DONE |
Darla L Downs
|
|
|
|
Issue and Print Permit | | | 4/19/2013 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/18/2013 | | 4/18/2013 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 4/18/2013 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/18/2013 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 4/3/2013 | | PEND |
|
|
|
On hold pending hydraulic verification.
|
Application received | | | 4/1/2013 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 1 2013 12:32PM
|
Plan assigned to (Tim) | 4/1/2013 | | 4/1/2013 | | DONE |
Tim Frost
|
|
|
|