Permit Information
Permit NumberFIR99-00654
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 520 S 9TH ST
Project NameSPR CONTEMPORARY THTR
Customer Number 
ePlanReviewNo
Description
(BOISE CONTEMPORARY THEATRE) Fire sprinklers substitute for 1-hr fire-resistive construction of the building. To fire sprinkler a former warehouse to an assembly occupancy (220 seat theater) with supporting uses. Work is to include undergound supply. A new 2nd level floor structure, and new 2nd level roof structure are being installed. All per approved drawings, engineering, and plan review conditions on file. The fire sprinkler system shall comply with NFPA 13 and 24, 1996 as regulated by the Fire Department.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled2/13/20022/13/20022/13/2002APASS
DetailsRick Jackson
Finaled by inspector at 2/13/2002 9:18:55 AM
INSP-Sprinkler Rough-in/Hydro5/5/20005/5/20005/5/2000AFAIL
DetailsRick Jackson
overspacing; cages for heads under stairs; lighting room needs additional head; 2nd floor by stair head within 4 inches of wall; calc and FM tag on riser; high temp head needed near heater on 2nd floor
INSP-Supply line flush4/26/20004/26/20004/26/2000PPASS
DetailsRick Jackson
flush okay
INSP-Sprinkler Rough-in/Hydro4/11/20004/11/20004/11/2000PPART
DetailsRick Jackson
basement area requires in concealed space under stairs at west end
INSP-Sprinkler Rough-in4/3/20004/3/20004/3/2000APART
DetailsRick Jackson
okay to cover music instruction rooms on north side only. cavity to be filled to keep concealed space under 6 inches. heads overspaced at tmep wall on 2nd floor.
Sprinkler Plan Check1/14/2000 2/4/2000 PASS
Provided calculations and modified piping for basement storage area to meet Ordinary Group 2 Hazard.
Miscellaneous action  2/4/2000 PASS
Basement modified piping and calculation plans taken to the front desk for calling and distribution.
INSP-Supply line flush1/26/20001/26/20001/26/2000 PASS
DetailsRick Jackson
this is to update the records - supply line cover and flush conducted a few months ago. both pass.
INSP-Sprinkler Rough-in/Hydro1/25/20001/25/20001/25/2000PPART
DetailsRick Jackson
underground hydro okay
Inspection Record Card- Bld12/23/199912/23/199912/23/1999 DONE
Telephone call  12/23/1999 DONE
talked to brad kilburn to verify plans are ready
Issue permit  12/23/1999 DONE
Sprinkler Plan Check12/22/1999 12/22/1999 PASS
Sprinkler Plan Check12/22/1999 12/22/1999 PASS
Miscellaneous action  12/22/1999 PASS
PLANS TAKEN TO THE FRONT DESK FOR PERMITTING
Telephone call  12/13/1999 FAIL
CONTACTED BRAD KILBURN CONCERNING PLAN ELIGIBLE
Sprinkler Plan Check12/8/1999 12/13/1999 FAIL
CANNOT READ PLANS CLEARLY FOR A REVIEW
Application received  12/8/1999 PASS
WATER SUPPLY PROVIDED BY UNITED WATER, THROUGH WHITE LEISURE CONSTRUCTION, FROM CARTER SOMMERSET.
INSP-Final Inspection11/22/199911/22/199911/22/1999ADONE
DetailsRick Jackson
Case Summary