GCM-Final | 5/21/2014 | 5/22/2014 | 5/22/2014 | P | PASS |
Dixie Fellows
|
|
|
Aaron ###-####..no card on site
|
GCM-Rough-in | 4/25/2014 | 4/28/2014 | 4/28/2014 | P | PASS |
Dixie Fellows
|
|
|
Aaron ###-####..r/i ok cover
|
GCM-Rough In & Pressure Test | 4/23/2014 | 4/24/2014 | 4/24/2014 | A | NR |
Dixie Fellows
|
|
|
Dustin ###-####..I WAITED ALL DAY BUT NOBODY CONTACTED ME ABOUT THE RESUBMITTALS
|
GCM-Rough-in | 4/18/2014 | 4/18/2014 | 4/18/2014 | P | PART |
Dixie Fellows
|
|
|
aaron ###-####...PARTIAL ONLY...OK TO INSULATE THE WALLS ONLY..NOT SHEETROCK UNTIL I GET THE RESUBMITTALS FROM THE ENGINEER...TALKED TO G/C AND STRUCTURAL INSPECTOR
|
GCM-Rough-in | 4/16/2014 | 4/16/2014 | 4/16/2014 | P | FAIL |
Dixie Fellows
|
|
|
The notes are on the plan table..NEED A NEW DRAWING STAMPED AND SIGNED SHOWING EXISTING FURNACE SUPPLYING HEAT AND COOLING TO NEW OFFICES, ETC
|
GCM-Rough In & Pressure Test | 4/14/2014 | 4/14/2014 | 4/14/2014 | P | PART |
Bill VanDegrift
|
|
|
Tom ###-#### 1-60# and 1-20# gas test ok 5# flue test ok need to resubmit a mechanical plan showing the system installed for review and approval
|
GCM-Pressure Test | 4/10/2014 | 4/11/2014 | 4/11/2014 | P | PASS |
Dixie Fellows
|
|
|
Aaron ###-####..20lb ok..60lb failed
|
Application received | | | 4/3/2014 | | DONE |
|
|
|
|