Final | 10/19/2000 | 10/20/2000 | 10/20/2000 | A | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/19/2000 at 13:03:56. Contact: ###-####.
|
Pressure Test | 7/22/2000 | 7/24/2000 | 7/24/2000 | P | PASS |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 07/22/2000 at 12:37:44. Contact: ###-####.
|
Rough-in | 7/20/2000 | 7/21/2000 | 7/21/2000 | A | PASS |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 07/20/2000 at 17:29:11. Contact: ###-####.
|
Pressure Test | 7/20/2000 | 7/21/2000 | 7/21/2000 | A | FAIL |
Dave Lightfoot
|
|
|
Scheduled by a contractor via Hello! on 07/20/2000 at 17:29:27. Contact: ###-####.
|
Application received | | | 7/18/2000 | | |
|
|
|
|
Issue & PRINT permit | | | 7/18/2000 | | DONE |
|
|
|
|