Final | 12/15/2000 | 12/15/2000 | 12/15/2000 | P | PASS |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 12/15/2000 at 09:12:29. Contact: ###-####.
|
Rough-in | 8/16/2000 | 8/16/2000 | 8/16/2000 | P | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 08/16/2000 at 08:05:53. Contact: ###-####.
|
Pressure Test | 8/16/2000 | 8/16/2000 | 8/16/2000 | P | PASS |
Alan Hauser
|
|
|
Scheduled by a contractor via Hello! on 08/16/2000 at 08:06:21. Contact: ###-####.
|
Rough-in | 8/15/2000 | 8/15/2000 | 8/15/2000 | P | FAIL |
Dixie Fellows
|
|
|
###-####
|
Pressure Test | 8/15/2000 | 8/15/2000 | 8/15/2000 | P | FAIL |
Dixie Fellows
|
|
|
PIPE UNDERSIZED TO EQ 8/15/2000 1:48:05 PM
|
Issue & PRINT permit | | | 8/15/2000 | | DONE |
|
|
|
|
Application received | | | 8/15/2000 | | |
|
|
|
|