Final | 10/16/2001 | 10/17/2001 | 10/17/2001 | P | PASS |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 10/16/2001 at 12:00:05. Contact: ###-####.
|
DOC - Permit Finaled | 10/17/2001 | 10/17/2001 | 10/17/2001 | P | PASS |
Steven Webb
|
|
|
Finaled by inspector at 10/17/2001 2:52:13 PM
|
Final | 10/16/2001 | 10/17/2001 | 10/16/2001 | A | CANC |
Steven Webb
|
|
|
Scheduled by a contractor via Hello! on 10/16/2001 at 10:48:44. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 10/16/2001 at 11:58:17.
|
Final | 10/15/2001 | 10/16/2001 | 10/16/2001 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/15/2001 at 15:49:32. Contact: ###-####. co 10/16/2001 11:51:52 AM corrections not done 10/16/2001 11:53:24 AM
|
Final | 10/4/2001 | 10/5/2001 | 10/5/2001 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 10/04/2001 at 14:18:23. Contact: ###-####. frame b-vent 2nd floor..complete ducts..kit exhaust n/r...complete f/p trim..need protection post at furn
10/5/2001 9:44:00 AM
|
Rough-in | 8/3/2001 | 8/3/2001 | 8/3/2001 | P | PASS |
Steven Webb
|
|
|
misty ###-#### re-insp r/i if failed please call
|
Rough-in | 8/1/2001 | 8/2/2001 | 8/2/2001 | P | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 08/01/2001 at 16:51:04. Contact: ###-####. still holes in r/a plenum at first floor 8/2/2001 2:02:40 PM
|
Pressure Test | 8/1/2001 | 8/2/2001 | 8/2/2001 | P | PASS |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 08/01/2001 at 16:51:21. Contact: ###-####.
|
Rough-in | 7/31/2001 | 8/1/2001 | 8/1/2001 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 07/31/2001 at 14:18:07. Contact: ###-####. seal r/a on 1st floor plenum 8/1/2001 11:55:36 AM
|
Pressure Test | 7/31/2001 | 8/1/2001 | 8/1/2001 | A | FAIL |
Dixie Fellows
|
|
|
Scheduled by a contractor via Hello! on 07/31/2001 at 14:18:31. Contact: ###-####.
|
Application received | | | 7/31/2001 | | |
|
|
|
|
Issue & PRINT permit | | | 7/31/2001 | | DONE |
|
|
|
|