Final | 8/13/2014 | 8/13/2014 | 8/13/2014 | P | PASS |
Alan Hauser
|
|
|
5# on flue and 20# on gas
|
Final | 8/11/2014 | 8/13/2014 | 8/13/2014 | A | FAIL |
Alan Hauser
|
|
|
still waiting for acca report, 5# test on flue and 20# test on gasline ok
|
Review - BUILDING | 8/1/2014 | 8/1/2014 | 8/1/2014 | | FAIL |
Troy James
|
|
|
This is actually the second review for maual j report.
|
Final | 6/19/2014 | 6/19/2014 | 6/19/2014 | P | FAIL |
Bill VanDegrift
|
|
|
This is a Flue Pressure test and Final Inspect. Our installers are installing today. Pls go as early as possible. Install Mgr, Allen, Ph is ###-####. Phone #: ###-#### >> Inspection requested via web by Mary LaFayette ACCA report required
|
Issue PAID IN FULL permit | | | 6/18/2014 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 6/18/2014 | | DONE |
|
|
|
This permit was created on the web by Mary LaFayette
|