First Notice | 7/14/2015 | 7/14/2015 | 11/20/2015 | | DONE |
Dixie Fellows
|
|
|
This permit finaled on the web by Dan Flaherty
|
Final | 7/14/2015 | 7/14/2015 | 7/14/2015 | A | PASS |
Dixie Fellows
|
|
|
Contact Stan ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty
|
Final | 6/18/2015 | 6/19/2015 | 6/19/2015 | A | PART |
Dixie Fellows
|
|
|
Stan/###-####/ final Phone #: ###-#### >> Inspection requested via web by Crystal Grant..temp occ ok
|
Final | 6/16/2015 | 6/16/2015 | 6/16/2015 | P | FAIL |
Dixie Fellows
|
|
|
Brian ###-####/ final Phone #: ###-#### >> Inspection requested via web by Crystal Grant...need venting specs for unit htr...complete condensate at unit htr...plumbing pipes to be 10' away from or 3' above fresh air into garage...protect line sets..secure condensing units on roof..raise unit htr flue (to close to intake)...
|
Final | 6/15/2015 | 6/16/2015 | 6/16/2015 | A | PEND |
Dixie Fellows
|
|
|
Please contact Stan ###-####/final inspection Phone #: ###-#### >> Inspection requested via web by Crystal Grant..stan will reschedule so brian can meet me at 1:00
|
Rough-in | 4/1/2015 | 4/1/2015 | 4/1/2015 | P | PASS |
Dixie Fellows
|
|
|
brian ###-####..ok for cover
|
Rough-in | 3/31/2015 | 4/1/2015 | 4/1/2015 | A | PEND |
Dixie Fellows
|
|
|
Brian ###-####/cover inspection Phone #: ###-#### >> Inspection requested via web by Crystal Grant..brian will be back at 1:00..i rescheduled for pm
|
Rough-in | 3/31/2015 | 3/31/2015 | 3/31/2015 | P | FAIL |
Dixie Fellows
|
|
|
Brian ###-####/cover inspection Phone #: ###-#### >> Inspection requested via web by Crystal Grant..duct connections not per manuf...unable to use tape per manuf
|
Rough-in | 3/24/2015 | 3/25/2015 | 3/25/2015 | A | FAIL |
Troy James
|
|
|
**Please provide 1hr notice contact Brian ###-####/rough in Phone #: ###-#### >> Inspection requested via web by Crystal Grant Need to have the three fire dampers installed per manufacturer and have on site. Ok to insulate per the builder request.
|
Rough-in | 3/24/2015 | 3/24/2015 | 3/24/2015 | P | FAIL |
Dixie Fellows
|
|
|
called Brian and he was in nampa..reschedule when he is on site
|
Rough-in | 3/24/2015 | 3/24/2015 | 3/24/2015 | P | CANC |
Dixie Fellows
|
|
|
Brian ###-####/ rough in inspection Phone #: ###-#### >> Inspection requested via web by Crystal Grant Inspection cancelled from web by: Crystal Grant
|
Rough-in | 2/23/2015 | 2/24/2015 | 2/24/2015 | A | CANC |
Bill VanDegrift
|
|
|
Stand ###-####/underground inspection of the radon pipe Phone #: ###-#### Inspection requested via web by Crystal Grant we don't regulate radon on commercial occupancies.
|
Issue PAID IN FULL permit | | | 2/23/2015 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 2/23/2015 | | DONE |
|
|
|
This permit was created on the web by Crystal Grant
|