Final | 1/16/2012 | 1/17/2012 | 1/17/2012 | A | PASS |
Jim Johnson
|
|
|
Please call Johny with questions ###-####. Door code 0475. Thank you. Phone #: ###-#### >> Inspection requested via web by Jennifer Alcala no sign off card on site
|
Final | 1/12/2012 | 1/13/2012 | 1/13/2012 | A | PART |
Jim Johnson
|
|
|
Please call Johny with questions ###-####. Thank you. Phone #: ###-#### >> Inspection requested via web by Jennifer Alcala need open front seat on water closet need expansion tank installed need to pipe T&P drain line to an approved location called contractor will recall when ready
|
Issue PAID IN FULL permit | | | 10/21/2011 | | DONE |
|
|
|
Payment received via Govolutions
|
Fees Due Hold | 10/13/2011 | | 10/21/2011 | | DONE |
|
|
|
|
Plumbing Rough-in | 9/30/2011 | 10/3/2011 | 10/3/2011 | A | PASS |
Jim Johnson
|
|
|
Please call Johny with questions ###-####. Thank you, Phone #: ###-#### >> Inspection requested via web by Jennifer Alcala
|
Plumbing Rough-in | 9/16/2011 | 9/20/2011 | 9/19/2011 | A | CANC |
Jim Johnson
|
|
|
Please call Johny with questions ###-####. Thank you. Phone #: ###-#### >> Inspection requested via web by Jennifer Alcala Inspection cancelled from web by: Jennifer Alcala
|
Plumbing Rough-in | 9/15/2011 | 9/15/2011 | 9/15/2011 | P | PART |
Jim Johnson
|
|
|
Please call Johny with questions ###-####. Thank you, Phone #: ###-#### >> Inspection requested via web by Jennifer Alcala as per 904.1 need to provide vent to meet the cross-sectional area of the required building drain need two two inch an d one 1 1/2 vent through roof for required building drain
|
Owner Supplied Equipment | | | 9/15/2011 | | |
|
|
|
|
Application received | | | 9/15/2011 | | DONE |
|
|
|
This permit was created on the web by Jennifer Alcala
|
First Notice | 1/17/2012 | 1/17/2012 | | | |
Jim Johnson
|
|
|
|