Inspections for the day of: Thursday, April 9, 2020.
Number of inspections: 6
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTroy Cobbley
TitleFIRE INSPECTOR
Phone #794-9483
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
FIR19-00815 INSP-Sprinkler Rough-in4/9/20204/9/20204/9/2020 3:08:49 PMPPASS
Rough-in passed. Tenting passed. Piping can be covered.
Re-inspection, as built is approved, FDC relocated. Please call James before heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
FIR20-00171 INSP-Sprinkler Rough-in4/9/20204/9/20204/9/2020 1:59:41 PMPPASS
Rough-in passed. Piping ok for cover. Heads at the new overhead door not complete yet.

Phone #: ###-#### Inspection requested via web by Sam Ball
GRD18-00092 FIRE-Final Inspection4/9/20204/9/20204/9/2020 12:40:05 PMAPASS
Life safety passed.
FIR19-00769 INSP-Final Inspection4/2/20204/9/20204/9/2020 11:12:24 AMPFAIL
Total trip time was 1:55, it can not exceed 60 seconds. Also need ceiling and pendant installed in the Data Room.

Please call Jim Lewis if you have any questions he is on site ###-#### Phone #: ###-#### Inspection requested via web by Joshua Hansen
FIR19-00769 INSP-Sprinkler Rough-in4/8/20204/9/20204/9/2020 10:01:29 AMAPASS
24 hour air test witnessed with no pressure loss.
Please give a Jim Lewis a call for inspection time. Phone #: ###-#### Inspection requested via web by Joshua Hansen
FIR19-00894 INSP-Sprinkler Rough-in/Hydro4/8/20204/9/20204/9/2020 10:01:00 AMAPASS
The underground hydro test was witnessed with no pressure loss.

Phone #: ###-#### Inspection requested via web by Sam Ball