INSP-Final Inspection | 11/24/2015 | 11/25/2015 | 11/25/2015 | P | PASS |
Jim Page
|
|
|
Supply line flush completed in May 2015, was finaled under FIR15-00036. Final inspection for underground complete.
|
INSP-Sprinkler Rough-in/Hydro | 2/12/2015 | 2/12/2015 | 2/12/2015 | P | FAIL |
Troy Cobbley
|
|
|
Underground flush failed due to United Water not having the water turned on.
|
INSP-Sprinkler Rough-in | 12/19/2014 | 12/19/2014 | 12/19/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line tie-in verified and approved for bury.
|
INSP-Sprinkler Rough-in | 12/9/2014 | 12/10/2014 | 12/10/2014 | P | PART |
Forrest France
|
|
|
UG fire supply line including the IBR okayed for bury. Thrust blocking poured while on site.
|
INSP-Sprinkler Rough-in | 12/8/2014 | 12/9/2014 | 12/9/2014 | P | CANC |
Forrest France
|
|
|
This is an ug to cover. Bryan is the contact. Thanks Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|