Permit Information
Permit NumberBLD17-00386
StatusFinaled
Name PERKINS CONSTRUCTION
Site Address 2855 W LOCKHEED LN
Project NameCity of Boise ARFF BLDG
Customer Number17-01549
ePlanReviewYes
Description
(CITY OF BOISE AIR RESCUE & FIRE FIGHTING STATION)(AT BOISE AIRPORT) (**GREEN BUILDING - EXPEDITED REVIEW**) ""PLAN MODIFICATION TO INCLUDE LEAVING THE EXISTING COMPUTER LAB AND REVISE THE INTERIOR CONFIGURATION OF THE BUILDING"" There are two permits associated with thie Eplan case (BLD17-01549) Project shall comply with the 2012 International Green Construction Code as adopted by City of Boise. This project includes the remodel and expansion of the existing Air Rescue and Fire Fighting Station at the Boise Airport. The project consists of 10,000 s.f. of remodeled living and office, and apparatus space and 4,337 s.f. of new equipment storage and work space, including a 3400 s.f. apparatus bay housing two fire-fighting vehicles. Approximately 3500 s.f. of existing vehicle bay and storge space will remain. Existing exterior finishes will be removed and replaced with new insulated metal panel siding and cmu wainscot. Project includes a partial TPO reroof of the existing building including additional roof insulation, as well as new TPO roofing for the addition. Project shall comply with the 2012 International Green Construction Code as adopted by City of Boise. This building is fully fire sprinklered and alarmed. Any alterations to the sprinkler system shall comply with NFPA 13 and 72 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 1/16/20203/3/2020 DONE
Meeting  1/16/2020 DONE
Per contact with Renee New with Boise Airport, all value should have been claimed on BLD17-00386. Minimal work was done under BLD17-01549 to establish square footage for tenant space addition and remodel. Majority of value (minus minimum value) was moved to BLD17-00386 per final value submitted. Credit for fees erraneously paid on BLD17-01549 are credited to BLD17-00386.
Permanent Occupancy  1/6/2020 DONE
BLD-Final12/5/201912/6/201912/6/2019APASS
DetailsJim Storey
Inspection requested via web by Ron Goff
FIRE-Final Inspection12/5/201912/5/201912/5/2019PPASS
DetailsTroy Cobbley
Life safety passed.
FIRE-Alarm Testing12/5/201912/5/201912/5/2019PCANC
DetailsTroy Cobbley
wrong inspection type scheduled.

life safety reinspection Phone #: ###-#### Inspection requested via web by Ron Goff
Change Expiration Date Only  10/15/2019 DONE
DetailsJason Blais
A 180 day extension approved. First extension for an issued permit.
CHANGE STATUS TO (ISS)  6/6/2019 DONE
Plan mod submittedon 4/30 was cancelled
Routing - FIRE5/20/20195/20/20196/4/2019 CANC
DetailsErika Akin
Plan mod will be removed and resubmitted as a seperate TI
Routing - MECHANICAL5/20/2019 5/21/2019 PASS
DetailsTroy James
Plan Modification Accepted  4/30/2019 DONE
Revision to tenant space that will be occupied by Fedex. These revisions include the addition of Fedex Office 138A, Fedex Break 138B, shower 138C, and restroom 138D. Modification in the Existing Bay 139 include the replacement of existing sloped concrete for an accessible egress path for the tenant.
BLD-Final2/14/20192/15/20192/15/2019PPART
DetailsBrandon Shaw
Temp. Occupancy for Phase 3 is approved...
FIRE-Final Inspection2/15/20192/15/20192/15/2019PPART
DetailsJim Page
Life fire safety inspection for Phase 3 complete. Will need to have access control comply with chapter 10 of IFC before final inspection of project.

Please call when at the gate Phone #: ###-#### Inspection requested via web by Harvey VanderVeen
FIRE-Final Inspection2/14/20192/15/20192/15/2019ACANC
DetailsJim Page
Please call when at the gate. Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
FIRE-Final Inspection10/26/201810/26/201810/26/2018PPART
DetailsTroy Cobbley
Life safety for phase 2 passed
BLD-Final10/24/201810/25/201810/25/2018PPASS
DetailsJim Storey
Temp. Occupancy for Phase 2 Phone #: ###-#### Inspection requested via web by Harvey VanderVeen first phase ok
FIRE-Final Inspection10/24/201810/25/201810/25/2018PFAIL
DetailsTroy Cobbley
Need small documents, need exit discharge lighting corrected as discussed, need fire alrm permit and fire sprinkler work completed.


Temp. Occupancy for Phase 2 Phone #: ###-#### Inspection requested via web by Harvey VanderVeen
FIRE-Alarm Testing10/24/201810/25/201810/24/2018ACANC
DetailsTroy Cobbley
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
FIRE-Final Inspection10/24/201810/25/201810/24/2018ACANC
DetailsTroy Cobbley
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
BLD-Final10/24/201810/25/201810/24/2018ACANC
DetailsJim Storey
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
FIRE-Final Inspection10/23/201810/24/201810/24/2018PCANC
DetailsTroy Cobbley
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
FIRE-Alarm Testing10/23/201810/24/201810/24/2018PCANC
DetailsTroy Cobbley
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
BLD-Final10/23/201810/24/201810/24/2018PCANC
DetailsJim Storey
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
Plan Reviewer's activity  10/24/2018 DONE
DetailsJason Blais
Received Preliminary Commissioning Report for first phase. Uploaded into ePlanReview case.
BLD-Final10/19/201810/23/201810/19/2018ACANC
DetailsJim Storey
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
FIRE-Final Inspection10/19/201810/22/201810/19/2018ACANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
BLD-Final10/18/201810/19/201810/19/2018PNR
DetailsJim Sly
Temporary Occupancy for Phase 2. Early afternoon if possible Thanks Phone #: ###-#### Inspection requested via web by Harvey VanderVeen
Need Fire Final 1st.
CHANGE STATUS TO (ISS)  8/23/2018 DONE
Plan Mod
Print Statement  8/22/2018 DONE
Expiration Notice8/17/20189/10/20188/17/2018 DONE
DetailsBrittany Hill
OVERRIDE  6/18/2018  
OVERRIDE  6/18/2018  
Plan assigned to (CDM)4/17/20184/17/20186/18/2018 PASS
DetailsCarl D Madsen
Plan Mod
Routing - PLAN CHECK6/4/2018 6/18/2018 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  6/18/2018 DONE
Permit Ready to Issue  6/18/2018 DONE
PLAN MOD
Routing - PLAN CHECK4/23/2018 5/29/2018 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL4/23/2018 5/23/2018 PASS
DetailsCarl D Madsen
Routing - PLANNING4/23/2018 5/23/2018 PASS
DetailsTodd Tucker
Routing - FIRE4/23/20184/23/20185/2/2018 PASS
DetailsErika Akin
Attached comments to case
Routing - PLUMBING4/23/2018 4/24/2018 PASS
DetailsBill VanDegrift
s.s. vents cannot connect to the flammible vapor venting system.
Routing - PUBLIC WORKS4/23/2018 4/23/2018 PASS
DetailsRachael Beierle
Routing - MECHANICAL4/23/2018 4/23/2018 PASS
DetailsTroy James
Plan Modification Accepted  4/17/2018 DONE
DetailsChristina Prado
Plan Mod - interior reconfiguration
Issue PAID IN FULL permit  9/13/2017 DONE
Print Occupancy Form  9/13/2017 DONE
Extend Review Timeline  8/11/2017 DONE
1st Approved 180 day Extension per Adele. See documents
Expiration Notice7/27/20178/17/20177/27/2017 DONE
DetailsBrittany Hill
OVERRIDE  5/19/2017  
Permit Ready to Issue  5/19/2017 DONE
DetailsChristina Prado
Need RP, - need
GC Form & met 8-31-17
Revised Certificate of Value for issuance met 8-31-17

DO NOT ISSUE WITHOUT BLD17-01549
Plan assigned to (CDM)3/1/20173/1/20175/18/2017 PASS
DetailsCarl D Madsen
1st comp. BOI Airport Fire Station remodel/addition
Routing - PLAN CHECK5/16/2017 5/18/2017 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL5/16/2017 5/18/2017 PASS
DetailsCarl D Madsen
PLANS/APPL TAKEN TO FRONT DESK  5/18/2017 DONE
Routing - PLAN CHECK4/27/2017 5/8/2017 FAIL
DetailsCarl D Madsen
Failed pending structural
Routing Off Site - STRUCTURAL4/27/2017 5/8/2017 FAIL
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL4/3/2017 4/20/2017 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK4/3/2017 4/20/2017 PASS
DetailsCarl D Madsen
Routing - FIRE4/3/20174/3/20174/3/2017 PASS
DetailsKatie Marron
Revised report attached to case.
Route to Impact Fee Review3/16/20173/19/20173/17/2017 PASS
DetailsTonya Wallace
Review requested for Commercial Permit
Routing Off Site - STRUCTURAL3/16/2017 3/16/2017 FAIL
DetailsCarl D Madsen
1st review completed  3/16/2017 FAIL
Routing - PLAN CHECK3/1/2017 3/16/2017 FAIL
DetailsCarl D Madsen
Routing - MECHANICAL3/1/2017 3/8/2017 PASS
DetailsTroy James
Routing PW Sewer Design3/1/2017 3/6/2017 PASS
DetailsKyle S. Rosenmeyer
Routing - FIRE3/1/20173/1/20173/3/2017 FAIL
DetailsKatie Marron
Report attached to case and emailed to architect.
Routing - Erosion and Sediment3/1/2017 3/3/2017 PASS
DetailsMelissa Jannusch
RP TBD. DI protection (11), contractor staging area, concrete washout.
Routing - PLANNING Land Div3/1/2017 3/2/2017 PASS
DetailsTodd Tucker
Routing - Addressing3/1/2017 3/1/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS3/1/2017 3/1/2017 PASS
DetailsMorgan Webb
Routing - PLUMBING3/1/2017 3/1/2017 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - Design Review3/1/2017 3/1/2017 PASS
DetailsAndrea Tuning
Intake Approval  3/1/2017 PASS
DetailsDavid Ferguson
Case Summary (BLD)  3/1/2017 DONE
Application received  2/24/2017 DONE
Application submitted via PDS Online on Feb 24 2017 11:00AM
Plan assigned to (CDM)4/30/20194/30/2019   
DetailsCarl D Madsen
Routing - PLAN CHECK5/20/2019    
DetailsCarl D Madsen