Permit Information
Permit NumberBLD17-01937
StatusFinaled
Name CONGER MANAGEMENT GROUP
Site Address 7455 W SWIFT LN
Project NameCole Storage - Office
Customer Number01937 & 02006 TO 02018
ePlanReviewYes
Description
(COLE SELF STORAGE PARTNERS, LLC / DBA WISE SPACE STORAGE – OFFICE BUILDING) (***14 BUILDING PERMITS UNDER BLD17-01937 IN EPLAN*** Permit to construct a new 635 sq. ft. office building and related site improvements. Scope of work includes: construction of a slab on grade concrete, concrete foundation, construction of steel stud framed exterior walls with metal siding, metal roof purlins with a metal roof, interior nonbearing walls to create an accessible restroom for the disabled, a vestibule and a closet, millwork, new electrical, plumbing work, mechanical work, site work, and interior finishes to be in compliance with Ch. 8 of the 2012 IBC. The building is not fire sprinklered. Note: Special Inspections Required see form 310. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 7/21/20188/7/2018 DONE
mailed 8-10-18
First Notice 7/2/20187/11/2018 DONE
mailed 7-12-18
Permanent Occupancy  6/22/2018 DONE
BLD-Final6/20/20186/21/20186/21/2018PPASS
DetailsJim Sly
Steve Phone #: ###-####
FIRE-Final Inspection6/20/20186/21/20186/21/2018APASS
DetailsTroy Cobbley
Life safety passed. Per the contractor the new inner gate, at the main gate, is also connected to the opticon system.

Steve Phone #: ###-####
BLD-Final6/5/20186/7/20186/7/2018APART
DetailsJim Sly
Steve Phone #: ###-####
Temp OK.
FIRE-Final Inspection6/5/20186/6/20186/6/2018PPART
DetailsTroy Cobbley
A temporary occupancy is being given until the permanant building designations have been mounted (A, B, C...ect.). The west most fire hydrant is being rotated per the fie captain.

Steve Phone #: ###-####
PubWorks Occupancy Approval6/6/20186/6/20186/6/2018 DONE
DetailsTiffany Lowery
FIRE-Final Inspection6/1/20186/4/20186/4/2018PFAIL
DetailsTroy Cobbley
Need the exit discharge, on the east Office building door repaired and provided with a secondary power source, Repair the exit sign/emergency light/exit discharge light in the west corridor of BLDG K, Provide testing of the Opticon system at the main gate. get fire dept approval for the west side fire hydrant (barrel points to bollard)

Steve Phone #: ###-####
BLD-Final5/23/20185/30/20185/30/2018ANR
DetailsJim Sly
Please call ahead for access - Steve Phone #: ###-####
Zoning Approval5/30/20185/30/20185/30/2018 PASS
DetailsSarah Schafer
FIRE-Final Inspection5/23/20185/29/20185/29/2018AFAIL
DetailsTroy Cobbley
This was for a partial inspection. Contractor is missing all of the small documents/review comments. I went to the job site twice before I was able to make contact. I noted that the fire dept access (20'-0") has not been met in many locations especially at the south end of the project site, there are possible turning radius issues in the same location. Non of the fire hydrants meet the minimum 3'-0" clearance rule, non of the building have the A, B, C designations, the main gate does not meet the 20' min. clearance and the opticon has not been installed/tested, there is a gate just in side the entrance on the right that does not meet the 20' min. clearance., no fire extinguishers have been installed in the storage areas, building address appears to be partialy blocked. Due to time constraints I was unable to test the exit signs/emergency lights/exit discharge lights for the storage buildings with interior corridors. Single action hardware needs to be installed on the office doors as discussed and exit signs/emergency lights/exit discharge lights are missing from the office. I spoke to both Ron and Adele and it appears a plan modification will be required showing the changes to the fire access lane widths/possible radius changes especially the large changes at the south end of the project

Please call ahead for access - Steve Phone #: ###-####
Meeting  4/27/2018 DONE
Per attached email from K Reed - name updated to add DBA
BLD-Framing/Rough-in3/26/20183/27/20183/27/2018APART
DetailsMike Jordan
Ken Phone #: ###-####. Interior steel stud framed walls ok and soffitt. Need the structural drawings for exterior bearing walls and roof prior to cover.
BLD-Foundation11/13/201711/14/201711/14/2017PNR
DetailsJim Sly
Dane Phone #: ###-####
Print Occupancy Form  9/22/2017 DONE
Print Occupancy Form  9/22/2017 DONE
Issue PAID IN FULL permit  9/22/2017 DONE
OVERRIDE  9/20/2017  
Plan assigned to (JG)6/21/20176/21/20179/20/2017 PASS
DetailsJavier Guzman
1st rev comp, 7/12 Cole Storage BLDG OFFICE ***EPLAN***
PLANS/APPL TAKEN TO FRONT DESK  9/20/2017 DONE
Permit Ready to Issue  9/20/2017 DONE
DetailsChristina Prado
ALL MET Need:GC Form
Revised Certificate of Value
RP-MET
DO NOT ISSUE WITH BLD17-01937, BLD17-02006 through 02018
Routing - PLAN CHECK9/11/2017 9/20/2017 PASS
DetailsJavier Guzman
Routing - FIRE9/11/20179/11/20179/19/2017 PASS
DetailsScott Arellano
Review comments attached to case
Routing Off Site - STRUCTURAL9/11/2017 9/16/2017 PASS
DetailsJavier Guzman
signed off in ePlan by AHJ Engineers Chris Holladay
Routing PW Drainage9/11/2017 9/16/2017 PASS
DetailsBrian Murphy
signed off in ePlan by PW Drainage Brian Murphy
Routing PW Street Lights9/11/2017 9/15/2017 PASS
DetailsTom Marshall
Please remember to sign off on all remaining 13 permits
Route to Impact Fee Review7/19/20177/22/20177/21/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  7/19/2017 DONE
DetailsJavier Guzman
Routing - PLAN CHECK6/21/2017 7/19/2017 PASS
DetailsJavier Guzman
Routing PW Street Lights6/21/2017 7/17/2017 FAIL
DetailsTom Marshall
Failed in ePlan by Street Lights Tom Marshall
Routing Off Site - STRUCTURAL6/21/2017 7/17/2017 FAIL
DetailsJavier Guzman
Failed in ePlan by AHJ Engineers Chris Holladay
Routing - PLANNING Land Div6/21/2017 7/13/2017 PASS
DetailsTodd Tucker
Routing - PLANNING6/21/2017 7/13/2017 PASS
DetailsLeon Letson
Routing - Design Review6/21/2017 7/10/2017 PASS
DetailsSarah Schafer
Routing PW Drainage6/21/2017 6/30/2017 FAIL
DetailsBrian Murphy
NEED CANAL OK.
Routing - PLUMBING6/21/2017 6/26/2017 PASS
DetailsBill VanDegrift
Routing PW Solid Waste6/21/2017 6/23/2017 PASS
Details
Project approved for commercial cart service.
Routing - MECHANICAL6/21/2017 6/22/2017 PASS
DetailsTroy James
Routing - FIRE6/21/20176/21/20176/21/2017 FAIL
DetailsScott Arellano
Report attached to case and emailed to architect.
Routing - Erosion and Sediment6/21/2017 6/21/2017 PASS
DetailsMelissa Jannusch
Plan approved. RP TBD
Routing - PUBLIC WORKS6/21/2017 6/21/2017 PASS
DetailsRachael Beierle
CONTACT WEST BOISE SEWER DISTRICT FOR PERMIT PRIOR TO CONSTRUCTION.
Routing - Addressing6/21/2017 6/21/2017 PASS
DetailsLaura Hunter
Address corrected to 7455 W Swift Ln per change of address on 5/26/17
Intake Approval  6/21/2017 PASS
Intake Approval  6/16/2017 FAIL
DetailsJulie Romig
1. 502 Application for each building with building area, occupant load, and value specific to each building.
2. Sheet C6 ESC plans indicated on checklist and Civil sheet index, but not uploaded. Please upload sheet in Drawing Folder.
Application received  6/14/2017 DONE
Application submitted via PDS Online on Jun 14 2017 7:19AM