BLD-Final | 7/12/2019 | 7/12/2019 | 7/12/2019 | P | PASS |
Dave Hannah
|
|
|
Request permit to be closed. Last note indicated that fire protection was needed in 2nd floor tenant office. Delta Fire pulled a permit and installed missing sprinkler coverage that has been signed off by the fire inspector. Thanks! Phone #: ###-#### Inspection requested via web by Brandon McCurdy
|
BLD-Final | 12/26/2018 | 12/27/2018 | 12/28/2018 | A | NR |
Dave Hannah
|
|
|
We were awaiting a final on electrical. Electrical Contractor went out of business. A new piggy back electrical permit was pulled to address the previous correction notice. The work is done, electrical is now signed off. Therefore, we request the building permit be signed off (final). Phone #: ###-#### Inspection requested via web by Brandon McCurdy. Needs fire sprinckler work and sign offs
|
BLD-Framing/Rough-in | 11/29/2017 | 11/29/2017 | 11/30/2017 | P | PART |
Dave Hannah
|
|
|
I will be picking up the current permit set dated 11/28/17 by 10:00 am. If we could do the framing inspection later morning to be sure I have the current permit set onsite that would be great. Thanks. Phone #: ###-#### Inspection requested via web by Brandon McCurdy basement food prep area A ok to cover
|
BLD-Framing/Rough-in | 11/28/2017 | 11/29/2017 | 11/29/2017 | A | CANC |
Dave Hannah
|
|
|
I will be picking up the current permit set dated 11/28/17 by 10:00 am. If we could do the framing inspection later morning to be sure I have the current permit set onsite that would be great. Thanks. Phone #: ###-#### Inspection requested via web by Brandon McCurdy
|
Issue PAID IN FULL permit | | | 9/8/2017 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/8/2017 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 7/13/2017 | 7/13/2017 | 8/15/2017 | | DONE |
Julie Romig
|
|
|
**1st Review Comp - Resubmit Rec'd 08/14 - L3 Montandon Building - Roof and HVAC Upgrades - Need permit 08/18. 08/20.
|
Routing - PLAN CHECK | 8/14/2017 | | 8/15/2017 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/15/2017 | | DONE |
|
|
|
Need GC Form - met
and Revised Cert of Value -met
|
Route to Impact Fee Review | 8/11/2017 | 8/14/2017 | 8/13/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 8/11/2017 | | DONE |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 7/13/2017 | | 8/11/2017 | | FAIL |
Julie Romig
|
|
|
See ePlanReview for corrections.
|
Routing Off Site - STRUCTURAL | 7/13/2017 | | 7/19/2017 | | PASS |
Julie Romig
|
|
|
|
Routing - PLUMBING | 7/13/2017 | | 7/14/2017 | | PASS |
Bill VanDegrift
|
|
|
1) provide cross connection protection for makeup water as required for fill and drain system.
|
Routing - MECHANICAL | 7/13/2017 | | 7/14/2017 | | PASS |
Troy James
|
|
|
|
Routing - Design Review | 7/13/2017 | | 7/14/2017 | | PASS |
Katelyn Menuge
|
|
|
CZC17-00205
|
Routing - Addressing | 7/13/2017 | | 7/14/2017 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 7/13/2017 | | 7/14/2017 | | PASS |
Beverly Mountain
|
|
|
|
Intake Approval | | | 7/13/2017 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 7/10/2017 | | FAIL |
Julie Romig
|
|
|
Need: 1. Structural calculations showing the existing roof can support the new mechanical equipment.
2. Mechanical COMcheck for new mechanical units.
|
Application received | | | 6/30/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 30 2017 3:32PM
|