Permit Information
Permit NumberBLD17-02193
StatusIssued
Name EKC INC
Site Address 242 N 8TH ST
Project NameFidelity Building - Roof HVAC
Customer Number17-005
ePlanReviewYes
Description
(FIDELITY BUILDING - ROOF HVAC) **The fire sprinkler system is used to substitute for 1-hr fire-resistance-rated construction of the building. Permit is to remove the existing mechanical units and install new rooftop mechanical units as well as mechanical improvements throughout the building. Walls will be added in Suite 210 on the 2nd floor to wall off an area for the future installation of mechanical ducts under a separate permit BLD17-02185 – floor is not to be penetrated or removed at this time. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. Separate fire sprinkler permits shall be obtained prior to beginning any modification or installation work on such systems. Scope of work permit only, certificate of compliance to be issued at completion of permit. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/12/20197/12/20197/12/2019PPASS
DetailsDave Hannah
Request permit to be closed. Last note indicated that fire protection was needed in 2nd floor tenant office. Delta Fire pulled a permit and installed missing sprinkler coverage that has been signed off by the fire inspector. Thanks! Phone #: ###-#### Inspection requested via web by Brandon McCurdy
BLD-Final12/26/201812/27/201812/28/2018ANR
DetailsDave Hannah
We were awaiting a final on electrical. Electrical Contractor went out of business. A new piggy back electrical permit was pulled to address the previous correction notice. The work is done, electrical is now signed off. Therefore, we request the building permit be signed off (final). Phone #: ###-#### Inspection requested via web by Brandon McCurdy. Needs fire sprinckler work and sign offs
BLD-Framing/Rough-in11/29/201711/29/201711/30/2017PPART
DetailsDave Hannah
I will be picking up the current permit set dated 11/28/17 by 10:00 am. If we could do the framing inspection later morning to be sure I have the current permit set onsite that would be great. Thanks. Phone #: ###-#### Inspection requested via web by Brandon McCurdy basement food prep area A ok to cover
BLD-Framing/Rough-in11/28/201711/29/201711/29/2017ACANC
DetailsDave Hannah
I will be picking up the current permit set dated 11/28/17 by 10:00 am. If we could do the framing inspection later morning to be sure I have the current permit set onsite that would be great. Thanks. Phone #: ###-#### Inspection requested via web by Brandon McCurdy
Issue PAID IN FULL permit  9/8/2017 DONE
Inspection Record Card- Bld  9/8/2017 DONE
Plan assigned to (JAR)7/13/20177/13/20178/15/2017 DONE
DetailsJulie Romig
**1st Review Comp - Resubmit Rec'd 08/14 - L3 Montandon Building - Roof and HVAC Upgrades - Need permit 08/18. 08/20.
Routing - PLAN CHECK8/14/2017 8/15/2017 PASS
DetailsJulie Romig
PLANS/APPL TAKEN TO FRONT DESK  8/15/2017 DONE
Permit Ready to Issue  8/15/2017 DONE
Need GC Form - met
and Revised Cert of Value -met
Route to Impact Fee Review8/11/20178/14/20178/13/2017 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  8/11/2017 DONE
DetailsJulie Romig
Routing - PLAN CHECK7/13/2017 8/11/2017 FAIL
DetailsJulie Romig
See ePlanReview for corrections.
Routing Off Site - STRUCTURAL7/13/2017 7/19/2017 PASS
DetailsJulie Romig
Routing - PLUMBING7/13/2017 7/14/2017 PASS
DetailsBill VanDegrift
1) provide cross connection protection for makeup water as required for fill and drain system.
Routing - MECHANICAL7/13/2017 7/14/2017 PASS
DetailsTroy James
Routing - Design Review7/13/2017 7/14/2017 PASS
DetailsKatelyn Menuge
CZC17-00205
Routing - Addressing7/13/2017 7/14/2017 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS7/13/2017 7/14/2017 PASS
DetailsBeverly Mountain
Intake Approval  7/13/2017 PASS
DetailsJavier Guzman
Intake Approval  7/10/2017 FAIL
DetailsJulie Romig
Need: 1. Structural calculations showing the existing roof can support the new mechanical equipment.
2. Mechanical COMcheck for new mechanical units.
Application received  6/30/2017 DONE
Application submitted via PDS Online on Jun 30 2017 3:32PM