BLD-Aging Inspection | 2/11/2020 | 2/11/2020 | 2/11/2020 | | PASS |
Jim Storey
|
|
|
Expires: 11/12/19
|
DOC - Permit Expired | 2/11/2020 | 2/11/2020 | 2/11/2020 | A | PASS |
Jim Storey
|
|
|
Expires: 11/12/19
|
BLD-Aging Inspection | 9/27/2019 | 9/27/2019 | 9/30/2019 | | PASS |
Jim Storey
|
|
|
Expires: 11/12/19
|
BLD-Aging Inspection | 5/16/2019 | 5/16/2019 | 5/16/2019 | | PASS |
Jim Storey
|
|
|
wip
|
Plan Reviewer's activity | | | 4/9/2019 | | DONE |
Julie Romig
|
|
|
Spoke with the tenant, Sundus, who is trying to get occupancy to open the market. She said some of the work had been done, but that she wanted to change the location of the Type I hood and some of the equipment being installed, although it was unclear where to. Told her that she would need to have building and mechanical inspectors sign off on the work that has been completed up to this point, and if the change was significant, the mechanical engineer would need to revise and resubmit the mechanical plans for the hood location. Notified Jim Storey that she should be scheduling an inspection.
|
BLD-Aging Inspection | 1/2/2019 | 1/2/2019 | 1/2/2019 | | PASS |
Jim Storey
|
|
|
wip
|
BLD-Aging Inspection | 8/21/2018 | 8/21/2018 | 8/21/2018 | | PASS |
Jim Storey
|
|
|
Expires: 10/06/18
|
BLD-Framing/Rough-in | 4/6/2018 | 4/9/2018 | 4/9/2018 | A | PASS |
Jim Storey
|
|
|
Rex Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/28/2018 | | DONE |
|
|
|
|
Expiration Notice | 3/20/2018 | 4/10/2018 | 3/20/2018 | | DONE |
Brittany Hill
|
|
|
|
Print Occupancy Form | | | 3/13/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/13/2018 | | DONE |
|
|
|
Need
GC Form
|
Telephone call | | | 3/13/2018 | | DONE |
|
|
|
Spoke with Rex informing him that this permit is ready and the fee amount due for issuance
|
Plan assigned to (JAR) | 10/10/2017 | 10/10/2017 | 3/12/2018 | | DONE |
Julie Romig
|
|
|
**1st Rev Comp - 2nd Rec'd 02/26 - 520 C of O Babylon Market
|
Routing - PLAN CHECK | 2/28/2018 | | 3/12/2018 | | PASS |
Julie Romig
|
|
|
2nd Review
|
Case Summary (BLD) | | | 3/12/2018 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/12/2018 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2018 | | DONE |
|
|
|
|
Routing - MECHANICAL | 3/9/2018 | | 3/9/2018 | | PASS |
Troy James
|
|
|
The gyro meat cooker is to be electric per Rex Nielsen
|
Routing - FIRE | 3/8/2018 | 3/8/2018 | 3/8/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case and plans
|
Routing - MECHANICAL | 3/2/2018 | | 3/6/2018 | | FAIL |
Troy James
|
|
|
See attached mechanical correction
|
Routing - PLUMBING | 2/28/2018 | | 3/6/2018 | | PASS |
Bill VanDegrift
|
|
|
S-1 is shown as being indirectly wasted on P-1
|
Routing - PUBLIC WORKS | 2/28/2018 | | 3/2/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing PW Environmental | 2/28/2018 | | 3/2/2018 | | PASS |
Rick Christenson
|
|
|
Grease Trap Shown
|
Plan resubmittals requested | | | 2/26/2018 | | DONE |
|
|
|
received 518 app, form 304, two copies of form 310 statement of special inspections, structural engineering, letter from mech engineer and calcs, plan sheets M0.0, M0.1, A1.0, M1.0, M2.0, P1.0, P2.0; taken to Julie Romig
|
Route to Impact Fee Review | 10/20/2017 | 10/23/2017 | 10/23/2017 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 10/20/2017 | | FAIL |
Julie Romig
|
|
|
Additional information required
|
Routing - PLAN CHECK | 10/19/2017 | | 10/20/2017 | | FAIL |
Julie Romig
|
|
|
Additional information is required.
|
Routing PW Environmental | 10/11/2017 | | 10/19/2017 | | FAIL |
Rick Christenson
|
|
|
Needs Grease Abatement.
|
Routing PW Sewer Rating | 10/19/2017 | | 10/19/2017 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Street Lights | 10/19/2017 | | 10/19/2017 | | PASS |
Tom Marshall
|
|
|
|
Routing - Addressing | 10/10/2017 | | 10/11/2017 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/10/2017 | | DONE |
|
|
|
|
Intake Approval | | | 10/10/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/10/2017 | | DONE |
|
|
|
|
Application received | | 10/10/2017 | | | |
|
|
|
|
Routing - PUBLIC WORKS | 10/10/2017 | | | | FAIL |
|
|
|
SEE ENVIRONMENTAL FOR FAIL
|