BLD-Final | 5/29/2018 | 5/29/2018 | 5/29/2018 | P | PASS |
Mike Jordan
|
|
|
garage door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 5/29/2018 | 5/29/2018 | 5/29/2018 | P | PASS |
Mike Jordan
|
|
|
Issues have been resolved.
|
BLD-Final | 5/15/2018 | 5/15/2018 | 5/15/2018 | P | DONE |
Mike Jordan
|
|
|
Door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle. Provide code compliant landing ?stepa from back slider to patio. Correction notice posted.
|
BLD-Blower Door Test Results | 5/15/2018 | 5/15/2018 | 5/15/2018 | P | DONE |
Mike Jordan
|
|
|
Door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle.
3.27
|
BLD-Energy code compliance | 3/19/2018 | 3/19/2018 | 3/19/2018 | A | PASS |
Mike Jordan
|
|
|
Please schedule early AM if possible. Thanks Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 3/16/2018 | 3/16/2018 | 3/16/2018 | A | PASS |
Mike Jordan
|
|
|
I am also having fire place inspected this morning. We have correction done. Please schedule for latter in the morning if you can. Thanks Phone #: ###-#### Inspection requested via web by Joel Hirtle. ok to insulate.
|
BLD-Framing/Rough-in | 3/14/2018 | 3/15/2018 | 3/15/2018 | P | FAIL |
Brandon Shaw
|
|
|
Fire blocking at Fireplace chase Need truss Engineering
|
BLD-Framing/Rough-in | 3/14/2018 | 3/14/2018 | 3/14/2018 | P | CANC |
Mike Jordan
|
|
|
Please schedule for latter PM, hvac inspection is happening in the AM.
Thanks Phone #: ###-#### Inspection requested via web by Joel Hirtle. Cancelled by contractor via phone call.
|
BLD-Framing/Rough-in | 3/12/2018 | 3/12/2018 | 3/12/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Mech. rough in inspection has failed.
|
BLD-Framing/Rough-in | 3/9/2018 | 3/9/2018 | 3/9/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Needs mech. rough in inspection.
|
BLD-Wall Bracing | 2/26/2018 | 2/27/2018 | 2/27/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Foundation | 1/24/2018 | 1/25/2018 | 1/25/2018 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Foundation | 1/23/2018 | 1/24/2018 | 1/24/2018 | P | NR |
Brandon Shaw
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 1/22/2018 | 1/23/2018 | 1/23/2018 | P | PASS |
Brandon Shaw
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 1/19/2018 | 1/22/2018 | 1/22/2018 | P | CANC |
Mike Jordan
|
|
|
Dane Phone #: ###-####. Cancelled per contractor via phone call.
|
BLD-Footing | 1/18/2018 | 1/19/2018 | 1/19/2018 | P | CANC |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 1/17/2018 | 1/18/2018 | 1/18/2018 | P | CANC |
Mike Jordan
|
|
|
Dane Phone #: ###-####. Cancelled b y contractor via phone call.
|
Issue PAID IN FULL permit | | | 1/10/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/10/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 1/9/2018 | | |
|
|
|
|
Routing - PLAN CHECK | 12/29/2017 | | 1/9/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/9/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 1/9/2018 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 12/13/2017 | | 1/9/2018 | | DONE |
Michael Hanson
|
|
|
12/15 sfd L1 ePlan - 1st review completed. RTA - wall bracing and structural deficiences. MDH
|
Routing - PLAN CHECK | 12/13/2017 | | 12/29/2017 | | FAIL |
Michael Hanson
|
|
|
Resubmittals did not resolve wall bracing changemark. MDH
|
Plan assigned to (BJM) | 12/4/2017 | 12/4/2017 | 12/13/2017 | | DEFR |
Brian McGowan
|
|
|
12/15 sfd L1 ePlan
|
Routing - PLAN CHECK | 12/4/2017 | | 12/13/2017 | | FAIL |
Brian McGowan
|
|
|
RTA - wall bracing and structural deficiences. MDH
|
Plan Reviewer's activity | | | 12/13/2017 | | DONE |
Michael Hanson
|
|
|
|
1st review completed | | | 12/13/2017 | | FAIL |
Michael Hanson
|
|
|
RTA - wall bracing and structural deficiences. MDH
|
Route to Impact Fee Review | 12/4/2017 | 12/7/2017 | 12/6/2017 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 12/4/2017 | | DONE |
|
|
|
|
Intake Approval | | | 12/4/2017 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/4/2017 | | DONE |
|
|
|
|
Routing - MECHANICAL | 12/4/2017 | | 12/4/2017 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/4/2017 | | 12/4/2017 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 12/4/2017 | | 12/4/2017 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/4/2017 | | 12/4/2017 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 11/22/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 22 2017 3:48PM
|