BLD-Final | 2/26/2020 | 3/3/2020 | 3/3/2020 | A | PASS |
Jim Storey
|
|
|
The building is the shop in the backyard. You can go around back. The dog Ruby will bark a few times, but is a sweetheart. Phone #: ###-#### Inspection requested via web by Michael McDonald
|
DOC - Permit Finaled | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 10/31/2019 | 10/31/2019 | 10/31/2019 | | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 6/19/2019 | 6/19/2019 | 6/19/2019 | | PASS |
Jim Storey
|
|
|
|
BLD - Resubmittal Approved | 2/1/2019 | 2/5/2019 | 2/5/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Michael McDonald work in progress ok
|
BLD-Framing/Rough-in | 6/21/2018 | 6/22/2018 | 6/22/2018 | A | PASS |
Jim Storey
|
|
|
Go through gate on S side of house, dog will bark, she is a sweetheart. However, everyone thinks that about their dog.. but she absolutely is. From prior rough-in inspection, rafter ties are installed, elec rough in complete. From rafters not landing on top plate, justify load and connection, I identified which ones and nailed a ~3"x3" 90 degree angled piece from the rafter to the top plate. Rafters next to floor joists are also nailed into floor joists. Phone #: ###-#### Inspection requested via web by Michael McDonald // saftey glass in slider at final will be required.
|
BLD-Framing/Rough-in | 5/29/2018 | 5/30/2018 | 5/30/2018 | A | FAIL |
Jim Storey
|
|
|
Will not be home, can walk around back. Dog will bark, she is a sweetheart. Phone #: ###-#### Inspection requested via web by Michael McDonald
|
OVERRIDE | | | 5/1/2018 | | |
|
|
|
|
Routing Walk-In (Zoning) | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | DONE |
Sue Cummings
|
|
|
modification - extended roof for covered area
|
Routing Walk-In (BLD) | 5/1/2018 | 5/1/2018 | 5/1/2018 | P | DONE |
Rob Patrick
|
|
|
|
Routing - PLAN CHECK | 5/1/2018 | | 5/1/2018 | | PASS |
Rob Patrick
|
|
|
|
Inspection Record Card- Bld | | | 5/1/2018 | | DONE |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 5/1/2018 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/1/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 5/1/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/1/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/1/2018 | | DONE |
|
|
|
|
BLD-Footing | 3/8/2018 | 3/13/2018 | 3/13/2018 | A | PASS |
Jim Storey
|
|
|
Footing Inspection Phone #: ###-#### Inspection requested via web by Michael McDonald
|
OVERRIDE | | | 2/13/2018 | | |
|
|
|
|
Routing Walk-In (BLD) | 2/13/2018 | 2/13/2018 | 2/13/2018 | A | DONE |
Josh Bogle
|
|
|
|
Routing Walk-In (Zoning) | 2/13/2018 | 2/13/2018 | 2/13/2018 | A | DONE |
Colleen T Carroll
|
|
|
|
Routing Walk-In (Zoning) | 2/13/2018 | 2/13/2018 | 2/13/2018 | P | PASS |
Susan Riggs
|
|
|
|
Routing - PLAN CHECK | 2/13/2018 | | 2/13/2018 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 2/13/2018 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 2/13/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 2/13/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 2/13/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/13/2018 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 2/12/2018 | 2/12/2018 | 2/12/2018 | A | FAIL |
Celine Acord
|
|
|
need updated site plan for driveway
|
Routing Walk-In (BLD) | 2/12/2018 | 2/12/2018 | 2/12/2018 | A | FAIL |
Josh Bogle
|
|
|
talked submittal requirements
|
Routing - PLAN CHECK | 2/12/2018 | | 2/12/2018 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 2/12/2018 | | DONE |
Josh Bogle
|
|
|
|
Application received | | 2/12/2018 | | | |
|
|
|
|