BLD-Final | 6/21/2019 | 6/24/2019 | 6/24/2019 | A | PASS |
Tony Young
|
|
|
Scott Phone #: ###-####-call for access
|
DOC - Permit Finaled | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | DONE |
Tony Young
|
|
|
Scott Phone #: ###-####-call for access// 4.2
|
BLD-Final | 6/20/2019 | 6/21/2019 | 6/21/2019 | A | PEND |
Tony Young
|
|
|
Scott-call for access Phone #: ###-####,, needs hillside,, then ok
|
PubWorks Occupancy Approval | 6/21/2019 | 6/21/2019 | 6/21/2019 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
|
BLD-Aging Inspection | 2/13/2019 | 2/13/2019 | 2/21/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 2/12/2019 | 2/12/2019 | 2/15/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Other | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | PASS |
Tony Young
|
|
|
wui soffit // scott johnson Phone #: ###-####
|
BLD-Energy code compliance | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Brandon Shaw
|
|
|
Scott Phone #: ###-####
|
BLD-Framing/Rough-in | 9/26/2018 | 9/27/2018 | 9/27/2018 | A | PASS |
Dave Hannah
|
|
|
Scott Phone #: ###-####
|
BLD-Wall Bracing | 8/30/2018 | 8/31/2018 | 8/31/2018 | A | PASS |
Brandon Shaw
|
|
|
Scott Phone #: ###-####
|
BLD-Conference | 7/27/2018 | 7/27/2018 | 7/27/2018 | A | DONE |
Brandon Shaw
|
|
|
At time of footing inspection, 6/28/18, all excavated dirt had been removed from site.
|
BLD-Foundation | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | PART |
Tony Young
|
|
|
Ryan Phone #: ###-####,, work in progress
|
BLD-Footing | 6/28/2018 | 6/28/2018 | 6/28/2018 | P | PASS |
Brandon Shaw
|
|
|
Brian Phone #: ###-####
|
PubWorks Subgrade Approval | 6/25/2018 | 6/25/2018 | 6/25/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Inspection Record Card- Bld | | | 6/7/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/7/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 5/24/2018 | | |
|
|
|
|
Telephone call | | | 5/24/2018 | | DONE |
|
|
|
Amy email e plan and i answered her-she wanted to know what else was needed and how much fees were
|
Routing PW Grading-Hillside | 5/24/2018 | | 5/24/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing - PLAN CHECK | 5/24/2018 | | 5/24/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 5/24/2018 | | DONE |
Christina Prado
|
|
|
Need
RP - met
|
Plan assigned to (M_H) | 3/16/2018 | | 5/24/2018 | | DONE |
Michael Hanson
|
|
|
04/05 sfd L2 ePlan. 1st review completed - 2nd review completed. Hillside and structural. 3rd review completed. pending hillside MDH
|
Routing PW Grading-Hillside | 5/17/2018 | | 5/17/2018 | | FAIL |
Melissa Jannusch
|
|
|
Align setbacks/ footing depths with geotech and civil. call and e-mail sent to Focus Engineering
|
Routing - PLAN CHECK | 5/1/2018 | | 5/1/2018 | | FAIL |
Michael Hanson
|
|
|
See comments from PW Hillside and provide structural calculations for review. MDH
|
Routing PW Grading-Hillside | 4/30/2018 | | 4/30/2018 | | FAIL |
Melissa Jannusch
|
|
|
See changemarks in ePlan
Provide calculations for walls or remove walls from plan
|
Plan Reviewer's activity | | | 4/4/2018 | | FAIL |
Michael Hanson
|
|
|
Hillside, structural, and energy deficiencies. MDH
|
1st review completed | | | 4/4/2018 | | FAIL |
Michael Hanson
|
|
|
Hillside, structural, and energy deficiencies. MDH
|
Routing - PLAN CHECK | 3/16/2018 | | 4/4/2018 | | FAIL |
Michael Hanson
|
|
|
Hillside, structural, and energy deficiencies. MDH
|
Routing PW Grading-Hillside | 3/16/2018 | | 3/21/2018 | | FAIL |
Melissa Jannusch
|
|
|
see changemark in ePlan
|
Routing - FIRE | 3/16/2018 | 3/16/2018 | 3/20/2018 | | PASS |
Erika Akin
|
|
|
Plans were reviewed for FD access, availability of hydrants and defensible space.
|
Route to Impact Fee Review | 3/16/2018 | 3/19/2018 | 3/19/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Erosion and Sediment | 3/16/2018 | | 3/19/2018 | | PASS |
Michael Zawacki
|
|
|
Site inspection required.
|
Routing - MECHANICAL | 3/16/2018 | | 3/19/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 3/16/2018 | | 3/19/2018 | | PASS |
Nicolette Womack
|
|
|
|
Routing - Addressing | 3/16/2018 | | 3/16/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/16/2018 | | 3/16/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/16/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/16/2018 | | DONE |
|
|
|
|
Intake Approval | | | 3/16/2018 | | PASS |
|
|
|
|
Intake Approval | | | 2/23/2018 | | FAIL |
Christina Prado
|
|
|
Need:
Stamped foundation plan
Engineering
ESC Narrative
Soil & GeoTech report
|
Application received | | | 2/13/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 13 2018 9:23AM
|