Issue PAID IN FULL permit | | | 3/30/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/30/2018 | | DONE |
|
|
|
|
Telephone call | | | 3/29/2018 | | DONE |
|
|
|
called Brian McNeel-rev cert of val is WAY different and just want to verify before i add the fees
|
Meeting | | | 3/29/2018 | | DONE |
|
|
|
ent an email to Dr. McNeel of what fees were due
|
Plan assigned to (RMH) | 3/19/2018 | 3/19/2018 | 3/26/2018 | | PASS |
Ron Hill
|
|
|
McNeel Eye Center L-2
|
Routing - PLAN CHECK | 3/19/2018 | | 3/26/2018 | | PASS |
Ron Hill
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/26/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/26/2018 | | DONE |
|
|
|
ALL MET
Need
GC Form
Revised Cert of Value
|
Route to Impact Fee Review | 3/22/2018 | 3/25/2018 | 3/23/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 3/19/2018 | 3/19/2018 | 3/22/2018 | | PASS |
Scott Arellano
|
|
|
Attached comments to case
|
1st review completed | | | 3/22/2018 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 3/19/2018 | | 3/20/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 3/19/2018 | | 3/19/2018 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 3/19/2018 | | PASS |
|
|
|
|
Application received | | | 3/13/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 13 2018 3:33PM
|