BLD-Final | 1/29/2019 | 1/30/2019 | 1/30/2019 | A | PASS |
Jim Sly
|
|
|
Garage Code: 1234, Fixed requested issues. Phone #: ###-#### Inspection requested via web by Braden Holbrook
|
DOC - Permit Finaled | 1/30/2019 | 1/30/2019 | 1/30/2019 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 1/25/2019 | 1/28/2019 | 1/28/2019 | A | FAIL |
Brandon Shaw
|
|
|
Post Blower Door test results... Seal all penetration in garage... Garage/man door to be self closing... Seal condensate line penetration, at rear of home, A/C unit... Post proper Third Party Cert. for Enery Code Compl and insulate crawl...
|
BLD-Wall cover | 11/20/2018 | 11/21/2018 | 11/21/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Braden Holbrook
|
BLD-Framing/Rough-in | 11/9/2018 | 11/13/2018 | 11/13/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: 2084478909 >> Inspection requested via mobile web by Braden Holbrook
|
BLD-Conference | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | PASS |
Jim Storey
|
|
|
Phone #: 2084478909 >> Inspection requested via mobile web by Braden Holbrook
|
Plan Modification Accepted | | | 11/7/2018 | | DONE |
|
|
|
New manual j
|
Routing - MECHANICAL | 11/7/2018 | | 11/7/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 10/9/2018 | 10/10/2018 | 10/10/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Braden Holbrook
|
BLD-Conference | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | PASS |
Jim Sly
|
|
|
Phone #: 2089723899 >> Inspection requested via mobile web by Larry O'Leary Foundation wall....OK.
|
BLD-Footing | 6/20/2018 | 6/20/2018 | 6/20/2018 | P | PASS |
Jim Sly
|
|
|
As late as possible Phone #: 2089723899 >> Inspection requested via mobile web by Larry O'Leary
|
Issue PAID IN FULL permit | | | 6/18/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/18/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 6/12/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 4/23/2018 | 4/23/2018 | 6/12/2018 | | DONE |
Brian McGowan
|
|
|
1st review complete. 5-4 sfd L1 ePlan
|
Routing - PLAN CHECK | 6/12/2018 | | 6/12/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 6/12/2018 | | DONE |
|
|
|
|
1st review completed | | | 5/3/2018 | | FAIL |
Brian McGowan
|
|
|
Need wall bracing calculations.
Need to verify conditioned or vented crawl space.
Insulation values need to match from Manual J to drawings.
|
Routing - PLAN CHECK | 4/23/2018 | | 5/3/2018 | | FAIL |
Brian McGowan
|
|
|
Need wall bracing calculations.
Need to verify conditioned or vented crawl space.
Insulation values need to match from Manual J to drawings.
|
Route to Impact Fee Review | 4/23/2018 | 4/26/2018 | 4/25/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 4/23/2018 | | 4/24/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 4/23/2018 | | 4/23/2018 | | PASS |
Sue Cummings
|
|
|
See redlines on site plan.
|
Routing - Addressing | 4/23/2018 | | 4/23/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 4/23/2018 | | 4/23/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/23/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/23/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/23/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/20/2018 | | FAIL |
|
|
|
Need Manual J, Elevations for all sides of structure and heights.(front & side).
|
Application received | | | 4/16/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 16 2018 3:03PM
|