BLD-Aging Inspection | 10/4/2019 | 10/4/2019 | 10/10/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 10/3/2019 | 10/3/2019 | 10/10/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Final | 5/22/2019 | 5/23/2019 | 5/23/2019 | P | NR |
Tony Young
|
|
|
Garage Code: 6365 Phone #: ###-#### Inspection requested via web by Jessica Bradley,, needs fire damper in bathroom supply
|
BLD-Blower Door Test Results | 5/22/2019 | 5/23/2019 | 5/23/2019 | P | DONE |
Tony Young
|
|
|
Garage Code: 6365 Phone #: ###-#### Inspection requested via web by Jessica Bradley,,, 5.8
|
BLD-Final | 5/21/2019 | 5/22/2019 | 5/22/2019 | A | PART |
Tony Young
|
|
|
Garage Code: 6365 Phone #: ###-#### Inspection requested via web by Jessica Bradley,, needs fire seperation in bathroom on garage,, needs compliant BD test
|
PubWorks Occupancy Approval | 5/22/2019 | 5/22/2019 | 5/22/2019 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works.
|
Routing - MECHANICAL | 2/22/2019 | | 2/22/2019 | | PASS |
Troy James
|
|
|
Revised manual j report
|
BLD-Energy code compliance | 2/20/2019 | 2/20/2019 | 2/20/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jessica Bradley
|
BLD-Framing/Rough-in | 2/20/2019 | 2/20/2019 | 2/20/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jessica Bradley
|
BLD-Framing/Rough-in | 2/12/2019 | 2/13/2019 | 2/13/2019 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Jessica Bradley,, ok to insulate,, need to fix roof leaks prior to insulation,, see paint,, straps, toe nail hangers,, nail truss braces max 6" o.c. ,, seal off fireplace chase from adjoining attic,, justify humidity in pool room?, etc.
|
BLD-Wall Bracing | 1/21/2019 | 1/22/2019 | 1/22/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jessica Bradley
|
BLD-Foundation | 10/25/2018 | 10/26/2018 | 10/26/2018 | P | PART |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo Lira,, work in progress
|
BLD-Footing | 10/25/2018 | 10/25/2018 | 10/25/2018 | A | PASS |
Tony Young
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate const.
|
PubWorks Subgrade Approval | 10/19/2018 | 10/19/2018 | 10/19/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. A footing inspection may now be scheduled with the Building Department. The applicant will need to comply with MTI’s recommendations listed in their footing certification report and provide compactions test results for the back filled areas under the compromised wall to public works for approval. The applicant will also need to provide to PW an approval letter from the structural designer of the wall (Carl Geiger) approving the wall.
|
Inspection Record Card- Bld | | | 9/26/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/26/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 9/18/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 7/20/2018 | 7/20/2018 | 9/18/2018 | | DONE |
Rob Patrick
|
|
|
08/08 sfd L2 ePlan...8/1 Failed: Multiple corrections required. 8/27 Failed: Comments not addressed.
|
Routing - PLAN CHECK | 9/18/2018 | | 9/18/2018 | | PASS |
Jenny Nelson
|
|
|
Per JJN and Adele. MDH
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/18/2018 | | DONE |
|
|
|
|
Routing - FIRE | 8/30/2018 | 8/30/2018 | 8/30/2018 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 8/28/2018 | | 8/28/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 8/27/2018 | | 8/27/2018 | | FAIL |
Rob Patrick
|
|
|
No comments were addressed.
|
1st review completed | | | 8/1/2018 | | FAIL |
Rob Patrick
|
|
|
Corrections Required
|
Routing - PLAN CHECK | 7/20/2018 | | 8/1/2018 | | FAIL |
Rob Patrick
|
|
|
Corrections Required
|
Routing PW Grading-Hillside | 7/23/2018 | | 7/31/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - FIRE | 7/26/2018 | 7/26/2018 | 7/26/2018 | | FAIL |
Tim Frost
|
|
|
a fire flow letter was provided.
The fire flow is insufficent.
|
Routing - FIRE | 7/20/2018 | 7/20/2018 | 7/25/2018 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
8/02 New SFH L2 ePlan
See attached review
|
Plan Reviewer's activity | | | 7/25/2018 | | DONE |
|
|
|
Waiting on Ron to stop by to ask about WUI on this project. Left him a text.
|
Plan Reviewer's activity | | | 7/25/2018 | | DONE |
|
|
|
Emailed Review
|
Route to Impact Fee Review | 7/20/2018 | 7/23/2018 | 7/23/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 7/20/2018 | | 7/23/2018 | | FAIL |
Troy James
|
|
|
Sent corrections to legends mech.
|
Routing - PLANNING | 7/20/2018 | | 7/23/2018 | | PASS |
Nicolette Womack
|
|
|
Walls reviewed under CFH18-00055 & 56
|
Routing - Addressing | 7/20/2018 | | 7/23/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/20/2018 | | 7/23/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 7/20/2018 | | 7/23/2018 | | PASS |
Michael Zawacki
|
|
|
Foothills lot, site prep inspection required.
|
Plans ACCEPTED BY PLAN TECH | | | 7/20/2018 | | DONE |
|
|
|
|
Intake Approval | | | 7/20/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/20/2018 | | DONE |
|
|
|
|
Intake Approval | | | 7/18/2018 | | FAIL |
|
|
|
Please provide a building cross section of the whole structure showing a cut through the building from the bottom of the footing through the roof (along with the wall section).
|
Intake Approval | | | 7/16/2018 | | FAIL |
|
|
|
Please upload all sheets in correct orientation for which they are formatted (landscape vs. portrait).
Please provide a cross section of the whole structure(footings to roof) and the foundation plan needs to be stamped and signed by an Idaho licensed engineer (hillside).
|
Application received | | | 7/13/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 13 2018 12:10PM
|
Intake Approval | | | 7/13/2018 | | FAIL |
|
|
|
NEED
ROTATE PLANS
CROSS SECTION
FOUNDATION PLAN STAMPED AND SIGNED
INSULATION TYPE
WALL STUDS
WALL COMPONENTS
CONNECTORS
RESCHECK
|