BLD-Final | 2/26/2019 | 2/28/2019 | 2/28/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 2/28/2019 | 2/28/2019 | 2/28/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 2/26/2019 | 2/28/2019 | 2/28/2019 | A | DONE |
Brandon Shaw
|
|
|
ACH50- 4.75
|
BLD-Energy code compliance | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 12/11/2018 | 12/13/2018 | 12/13/2018 | A | FAIL |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall c/n on site do not insulate
|
Plan Modification Accepted | | | 11/30/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 11/30/2018 | | 11/30/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 11/29/2018 | 11/29/2018 | 11/29/2018 | P | PASS |
Dave Hannah
|
|
|
Eber Phone #: ###-####
|
BLD-Wall Bracing | 11/28/2018 | 11/28/2018 | 11/29/2018 | P | NR |
Dave Hannah
|
|
|
SHEAR // EVER Phone #: ###-#### missing two hold downs and needs to add stapels to panels
|
BLD-Foundation | 9/28/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Dave Hannah
|
|
|
WALL // Jose Phone #: ###-####
|
BLD-Footing | 9/28/2018 | 9/28/2018 | 9/28/2018 | P | PASS |
Dave Hannah
|
|
|
Jose Phone #: ###-####
|
PubWorks Subgrade Approval | 9/27/2018 | 9/27/2018 | 9/27/2018 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 9/18/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 9/12/2018 | 9/12/2018 | 9/18/2018 | | DONE |
Brian McGowan
|
|
|
Minimal time, no additional fee required for Plan Check.
|
CHANGE STATUS TO (ISS) | | | 9/18/2018 | | DONE |
|
|
|
per BJM no plan mod required
|
Inspection Record Card- Bld | | | 9/18/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/18/2018 | | 9/18/2018 | | PASS |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 9/18/2018 | | DONE |
|
|
|
per BJM-no fees due for plan mod
|
Routing - PLANNING | 9/17/2018 | | 9/17/2018 | | PASS |
Nicolette Womack
|
|
|
|
Plan Modification Accepted | | | 9/12/2018 | | DONE |
|
|
|
modification to site plan
|
CHANGE STATUS TO (REV) | | | 9/12/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/30/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/30/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 8/29/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 8/8/2018 | 8/8/2018 | 8/29/2018 | | DONE |
Brian McGowan
|
|
|
08/27 sfd L2 ePlan
|
Routing - PLAN CHECK | 8/8/2018 | | 8/29/2018 | | PASS |
Brian McGowan
|
|
|
|
Routing PW Grading-Hillside | 8/29/2018 | | 8/29/2018 | | CANC |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
|
1st review completed | | | 8/29/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2018 | | DONE |
Brian McGowan
|
|
|
|
Override - Parcel Holds | | | 8/29/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 8/29/2018 | | DONE |
|
|
|
met
|
Routing - PLANNING | 8/27/2018 | | 8/27/2018 | | PASS |
Nicolette Womack
|
|
|
|
Routing - FIRE | 8/13/2018 | 8/13/2018 | 8/24/2018 | | PASS |
Erika Akin
|
|
|
Fire area 3529, Fire flow 1000 gpm, plans were reviewed for hydrant availability, FD access and defensible space
|
Plan Reviewer's activity | | | 8/24/2018 | | DONE |
Brian McGowan
|
|
|
Uploaded new sheets and rerouted to Planning
|
Route to Impact Fee Review | 8/8/2018 | 8/11/2018 | 8/9/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 8/8/2018 | | 8/8/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/8/2018 | | 8/8/2018 | | FAIL |
Sue Cummings
|
|
|
Two areas encroching into setbacks
|
Routing - Addressing | 8/8/2018 | | 8/8/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/8/2018 | | 8/8/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/8/2018 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 8/8/2018 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/8/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/8/2018 | | PASS |
|
|
|
|
Intake Approval | | | 8/3/2018 | | FAIL |
|
|
|
Wrong code year for IECC
|
Application received | | | 7/31/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 31 2018 2:43PM
|