Permit Information
Permit NumberBLD18-03141
StatusIssued
Name KNIGHT INDUSTRIAL INC
Site Address 618 N ALLUMBAUGH ST
Project NameDarigold
Customer NumberBLD18-03425 FOUNDATION
ePlanReviewNo
Description
(DARIGOLD SUGER ROOM ADDITION) The insulated metal panel engineered connection is a deferred submittlal. Permit for the construction of a new 528 sq. ft. building and the installation of two new liquid sugar tanks within the new structure. New mechanical and plumbing will also be installed. This space is heated only for the products stored and not for human comfort and the envelop is not required to comply with the current energy code per ordinance. This is a fully fire sprinklered building for unlimited area. Any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/7/20191/8/20191/8/2019PPEND
DetailsMike Jordan
Matthew Phone #: ###-####. Final ok. Pending plumbing final.
FIRE-Final Inspection1/7/20191/8/20191/8/2019APASS
DetailsTroy Cobbley
Life safety passed.


Matthew Phone #: ###-####
BLD-Final12/14/201812/17/201812/17/2018ANR
DetailsMike Jordan
Mathew Phone #: ###-####-may need mechanical permit
FIRE-Final Inspection12/14/201812/14/201812/14/2018PFAIL
DetailsTroy Cobbley
Provide fire extinguisher with current inspection tag mounted as discussed.

Mathew Phone #: ###-####
Issue PAID IN FULL permit  10/18/2018 DONE
Permit Ready to Issue  10/2/2018 DONE
DetailsChristina Prado
Need
Revised Value to remove foundation portion, then calculate fees
Telephone call  10/2/2018 DONE
Called GC to advise permit is ready, fees to be set once revised valuation is received
Route to Impact Fee Review10/1/201810/4/201810/1/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Plan assigned to (CDM) 8/31/201810/1/2018 PASS
DetailsCarl D Madsen
Sugar Room Addition
PLANS/APPL TAKEN TO FRONT DESK  10/1/2018 DONE
Case Summary (BLD)  10/1/2018 DONE
Print Occupancy Form  10/1/2018 DONE
Routing - FIRE9/17/20189/17/20189/28/2018 PASS
DetailsErika Akin
Attached comments to case and plans
1st review completed  9/28/2018 DONE
Routing Off Site - STRUCTURAL9/15/2018 9/24/2018 PASS
DetailsCarl D Madsen
Stapley
Case Summary (BLD)  9/15/2018 DONE
Case Summary (BLD)  9/15/2018 DONE
Routing Off Site - STRUCTURAL8/31/2018 9/15/2018 FAIL
DetailsCarl D Madsen
Routing - PLAN CHECK9/10/2018 9/15/2018 PASS
DetailsCarl D Madsen
Plan resubmittals received  9/13/2018 DONE
Three copies of sheets G1, S1.1, S1.2, S2, S3.1 and S3.2. Taken to Carl M. customer emailed in calcs and installation guide to Carl M.
Routing - MECHANICAL  9/10/2018 PASS
Routing - PLUMBING  9/10/2018 PASS
Plan resubmittals received  9/7/2018 DONE
Three copies of sheet S4. taken to Carl M
Routing PW Environmental8/31/2018 9/5/2018 PASS
DetailsRick Christenson
Routing - Design Review  9/5/2018 PASS
DetailsAndrea Tuning
Routing - PUBLIC WORKS8/31/2018 9/5/2018 PASS
DetailsRachael Beierle
WEST BOISE SEWER DISTRICT.
Routing - Addressing8/31/2018 8/31/2018 PASS
DetailsDoug Chausow
Routing - Erosion and Sediment8/28/2018 8/28/2018 PASS
DetailsAndy J. Long
ESC plan waiver request approved. Designate certified RP for project. Site preparation inspection required.
Plans ACCEPTED BY PLAN TECH  8/28/2018 DONE
Recd Pcfee & Taken To Pln CK  8/28/2018 DONE
Intake Approval  8/28/2018 PASS
DetailsJavier Guzman
Application received 8/28/2018