BLD-Final | 5/30/2019 | 5/30/2019 | 5/30/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
DOC - Permit Finaled | 5/30/2019 | 5/30/2019 | 5/30/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 5/29/2019 | 5/30/2019 | 5/30/2019 | A | FAIL |
Mike Jordan
|
|
|
C of O Phone #: ###-#### Inspection requested via web by James Jackson. Provide code compliant handrail on stairs in garage. Does not terminate above lowest riser.
|
BLD-Blower Door Test Results | 5/29/2019 | 5/30/2019 | 5/30/2019 | A | DONE |
Mike Jordan
|
|
|
3.1
|
BLD-Final | 5/28/2019 | 5/29/2019 | 5/29/2019 | P | NR |
Tony Young
|
|
|
C of O Phone #: ###-#### Inspection requested via web by James Jackson,, guard rail,, fire caulk,, no access
|
BLD-Energy code compliance | 2/18/2019 | 2/19/2019 | 2/19/2019 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Framing/Rough-in | 2/12/2019 | 2/13/2019 | 2/13/2019 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson,, ok to insulate,, see minor corrections
|
BLD-Wall Bracing | 1/28/2019 | 1/28/2019 | 1/28/2019 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson,, will verify hold downs at frame inspection
|
BLD-Wall Bracing | 1/10/2019 | 1/11/2019 | 1/11/2019 | A | PART |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson shear ok need to check hd hold downs at framing
|
BLD-Foundation | 11/29/2018 | 11/29/2018 | 11/29/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 11/27/2018 | 11/27/2018 | 11/27/2018 | P | PASS |
Tony Young
|
|
|
Pour time 2pm- Serige Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/13/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/13/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 11/9/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 10/15/2018 | 10/15/2018 | 11/9/2018 | | DONE |
Jenny Nelson
|
|
|
10/26 sfd L1 ePlan. 1st review complete 10/25 Spread footings, tall wall engineering, shear wall calculations, second floor smoke and CO detectors, verify garage headers
|
Routing - MECHANICAL | 11/9/2018 | | 11/9/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLAN CHECK | 11/9/2018 | | 11/9/2018 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2018 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 11/9/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 11/5/2018 | | 11/5/2018 | | PASS |
Sue Cummings
|
|
|
Again
|
1st review completed | | | 10/25/2018 | | FAIL |
Jenny Nelson
|
|
|
Spread footings, tall wall engineering, shear wall calculations, second floor smoke and CO detectors, verify garage headers
|
Routing - PLANNING | 10/25/2018 | | 10/25/2018 | | PASS |
Sue Cummings
|
|
|
Street loaded driveway per Hal and Cody. Maximum driveway width in front setback is 33 ft.
|
Routing - PLAN CHECK | 10/15/2018 | | 10/25/2018 | | FAIL |
Jenny Nelson
|
|
|
|
Route to Impact Fee Review | 10/15/2018 | 10/18/2018 | 10/16/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 10/15/2018 | | 10/16/2018 | | FAIL |
Chad Schwendiman
|
|
|
Need to show fresh air ventilation to both furnaces on both the Building analysis and floor plan’s
|
Plans ACCEPTED BY PLAN TECH | | | 10/15/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/15/2018 | | DONE |
|
|
|
|
Intake Approval | | | 10/15/2018 | | PASS |
|
|
|
|
Routing - Addressing | 10/15/2018 | | 10/15/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/15/2018 | | 10/15/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 10/12/2018 | | FAIL |
|
|
|
-Please provide a REScheck or prescriptive method on the plans.
-The demo permit for this parcel needs to be issued before we can give impact fee credits for this new build.
|
Application received | | | 9/20/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 20 2018 4:08PM
|
Routing - PLANNING | 10/15/2018 | | | | FAIL |
|
|
|
Alley loaded parking is required when an alley is available.
|