Information based on query as of Monday, May 6, 2024.
Permit Information
Permit NumberBLD18-03575
StatusFinaled
Name CBH HOMES
Site Address 7014 W SPUR ST
Project NameSonoma 4-2 Fork South
Customer Number 
ePlanReviewYes
Description
**PRESCRIPTIVE ENERGY METHOD** Permit for the construction of a new 2539 sq. ft., two story (first story 2275 sq. ft., second story 264 sq. ft.) single family dwelling with 4 bedrooms, 2 bathrooms, approximately 138 sq. ft. of covered patio/porch and a 705 sq. ft. attached garage per the approved plans and any notations. R-1C zoning and setbacks per planning. JJN
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/3/20194/4/20194/4/2019PPASS
DetailsMike Jordan
Door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle
DOC - Permit Finaled4/4/20194/4/20194/4/2019PPASS
DetailsMike Jordan
BLD-Final2/21/20192/21/20192/21/2019PNR
DetailsMike Jordan
door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle. Needs MEP finals first.
BLD-Energy code compliance2/12/20192/14/20192/14/2019PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD-Framing/Rough-in2/12/20192/14/20192/14/2019PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD-Framing/Rough-in2/11/20192/12/20192/12/2019PFAIL
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Reinstall the removed OSB from the shear wall behind stairs at plumbing and dryer vent. OK to insulate.
BLD-Wall Bracing1/28/20191/30/20191/30/2019PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD-Footing1/7/20191/7/20191/7/2019PPART
DetailsMike Jordan
Scott Phone #: ###-####
Issue PAID IN FULL permit  12/17/2018 DONE
Inspection Record Card- Bld  12/17/2018 DONE
OVERRIDE  10/31/2018  
Plan assigned to (J_N)10/8/201810/8/201810/31/2018 DONE
DetailsJenny Nelson
10/19 sfd L1 ePlan. 2nd review, still need second floor framing. 1st Review complete 10/19, wall bracing calculations, second floor framing
Routing - PLAN CHECK10/31/2018 10/31/2018 PASS
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  10/31/2018 DONE
DetailsJenny Nelson
Permit Ready to Issue  10/31/2018 DONE
met
Routing - PLAN CHECK10/23/2018 10/23/2018 FAIL
DetailsJenny Nelson
1st review completed  10/19/2018 FAIL
DetailsJenny Nelson
Wall bracing calculations, second floor framing
Routing - PLAN CHECK10/8/2018 10/19/2018 FAIL
DetailsJenny Nelson
Route to Impact Fee Review10/8/201810/11/201810/9/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL10/8/2018 10/9/2018 PASS
DetailsTroy James
Routing - PLANNING10/8/2018 10/9/2018 PASS
DetailsColleen T Carroll
Routing - Addressing10/8/2018 10/9/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS10/8/2018 10/9/2018 PASS
DetailsMorgan Webb
Plans ACCEPTED BY PLAN TECH  10/8/2018 DONE
Intake Approval  10/8/2018 PASS
Recd Pcfee & Taken To Pln CK  10/8/2018 DONE
Application received  9/27/2018 DONE
Application submitted via PDS Online on Sep 27 2018 2:08PM
Intake Approval  9/27/2018 FAIL
MISSING
ROOF FRAMING
DOCUMENTS IN DOCUMENTS FOLDER