BLD-Framing/Rough-in | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PASS |
Dave Hannah
|
|
|
wall kicker -between 12 and 2:30 Keith Phone #: ###-####
|
FIRE-Final Inspection | 12/17/2018 | 12/17/2018 | 12/17/2018 | P | PASS |
Adele J Schaffeld-Griffin
|
|
|
wall kicker -between 12 and 2:30 Keith Phone #: ###-####
|
BLD-Framing/Rough-in | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Bob Archibald
|
|
|
Call 30 mins before // keith Phone #: ###-####. Exterior cover only. electrical rough in approval required prior to interior office cover.
|
Fees Due Hold | 10/23/2018 | | 10/24/2018 | | DONE |
Christina Prado
|
|
|
|
Issue & PRINT to be Invoiced | | | 10/22/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/22/2018 | | |
|
|
|
|
Plan assigned to (JG) | 10/16/2018 | 10/16/2018 | 10/19/2018 | | PASS |
Javier Guzman
|
|
|
10/19 L1 2nd Floor PDS Remodel ePlan
|
Routing - PLAN CHECK | 10/16/2018 | | 10/19/2018 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 10/19/2018 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/19/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/19/2018 | | DONE |
|
|
|
NEED
GC FORM
REVISED VALUE
|
Intake Approval | | | 10/15/2018 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 10/10/2018 | | FAIL |
Javier Guzman
|
|
|
Provide and upload the following:
• Provide a completed 518 checklist
• Provide a wall sections to show interior top of wall bracing method
|
Application received | | | 10/1/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 1 2018 2:03PM
|