BLD-Energy code compliance | 5/23/2019 | 5/24/2019 | 5/24/2019 | A | PASS |
Dave Hannah
|
|
|
after 930 // Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 5/13/2019 | 5/14/2019 | 5/14/2019 | A | PASS |
Dave Hannah
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 4/23/2019 | 4/24/2019 | 4/24/2019 | A | NR |
Dave Hannah
|
|
|
Jim Phone #: ###-####
|
BLD-Wall Bracing | 4/19/2019 | 4/22/2019 | 4/22/2019 | P | PART |
Jim Sly
|
|
|
late as possible // Jim Phone #: ###-#### Exterior shear nailing only........OK.
|
BLD-Foundation | 12/21/2018 | 12/24/2018 | 12/24/2018 | A | PART |
Jim Storey
|
|
|
Eric Phone #: ###-#### wip
|
BLD-Footing | 12/19/2018 | 12/20/2018 | 12/20/2018 | A | PASS |
Dave Hannah
|
|
|
Pouring at 11 am. **Eric Phone #: ###-####
|
OVERRIDE | | | 11/19/2018 | | |
|
|
|
|
Routing Walk-In (BLD) | 11/19/2018 | 11/19/2018 | 11/19/2018 | A | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 11/13/2018 | 11/13/2018 | 11/19/2018 | | PASS |
Josh Bogle
|
|
|
11/19 garage, paper - 1st done
|
Routing - PLAN CHECK | 11/19/2018 | | 11/19/2018 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 11/19/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 11/19/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/19/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 11/19/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/19/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/13/2018 | | 11/15/2018 | | FAIL |
Josh Bogle
|
|
|
needs #310, dimensioned Section View, & braced wall info
|
1st review completed | | | 11/15/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing Walk-In (Zoning) | 11/13/2018 | 11/13/2018 | 11/13/2018 | A | PASS |
KayCee Babb
|
|
|
|
Routing Walk-In (BLD) | 11/13/2018 | 11/13/2018 | 11/13/2018 | A | PASS |
Josh Bogle
|
|
|
applicant dropped off to be reviewed as a level 2
|
Application received | | 11/13/2018 | | | |
|
|
|
|