Information based on query as of Tuesday, June 18, 2024.
Permit Information
Permit NumberBLD19-00131
StatusFinaled
Name BLACKROCK HOMES LLC
Site Address 2542 E WARM SPRINGS AVE
Project NameWinslow 18B
Customer Number 
ePlanReviewYes
Description
***W.U.I. FOOTHILLS ZONE A: NON-COMBUSTIBLE MATERIALS AND CLASS "A" ROOF REQUIRED*** Permit for the construction of a new 1918 sq. ft., one story single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 280 sq. ft. of covered patio/porch and a 649 sq. ft. attached garage per the approved plans and any notations. Rescheck Energy Compliance. R-1C zoning and setbacks per planning. ***RDP*** A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions. FIRE SPRINKLERS ARE NOT REQUIRED. LGM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/17/201910/21/201910/21/2019APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Clint Wall
DOC - Permit Finaled10/21/201910/21/201910/21/2019PPASS
DetailsBrandon Shaw
BLD-Blower Door Test Results10/17/201910/21/201910/21/2019ADONE
DetailsBrandon Shaw
ACH50- 4.7
BLD-Energy code compliance8/13/20198/16/20198/16/2019APASS
DetailsBrandon Shaw
Phone #: ###-#### Inspection requested via web by Clint Wall
BLD-Framing/Rough-in8/13/20198/14/20198/14/2019APASS
DetailsBrandon Shaw
OK to insulate...
BLD-Wall Bracing7/30/20197/30/20197/30/2019PPASS
DetailsBrandon Shaw
& fascia - Jorge Phone #: ###-####
BLD-Foundation4/1/20194/1/20194/1/2019PPASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing3/28/20193/29/20193/29/2019APASS
DetailsBrandon Shaw
Work in progress...
PubWorks Subgrade Approval3/27/20193/27/20193/27/2019 DONE
DetailsMelissa Jannusch

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
Inspection Record Card- Bld  1/25/2019 DONE
Issue PAID IN FULL permit  1/25/2019 DONE
Meeting  1/24/2019 DONE
Emailed Josh to inform him the fire plan check fee was missed and once that is paid we can issue the permits.
OVERRIDE  1/17/2019  
Routing - FIRE1/16/20191/16/20191/17/2019 PASS
DetailsLee G Meredith
Fire sprinklers are not required.
Plan assigned to (RDP)1/15/20191/15/20191/17/2019 DONE
DetailsRob Patrick
Differed from Brian on 1/15. 1/16, review complete just need Fire to sign off.
Routing - PLAN CHECK1/15/2019 1/17/2019 PASS
DetailsRob Patrick
1st review completed  1/17/2019 DONE
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  1/17/2019 DONE
DetailsRob Patrick
Permit Ready to Issue  1/17/2019 DONE
Routing - MECHANICAL1/14/2019 1/16/2019 PASS
DetailsTroy James
Route to Impact Fee Review1/14/20191/17/20191/15/2019 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Plan assigned to (BJM)1/14/20191/14/20191/15/2019 DEFR
DetailsBrian McGowan
01/25 sfd ePlan L1
Plans ACCEPTED BY PLAN TECH  1/14/2019 DONE
Intake Approval  1/14/2019 PASS
Recd Pcfee & Taken To Pln CK  1/14/2019 DONE
Routing - PLANNING1/14/2019 1/14/2019 PASS
DetailsColleen T Carroll
Routing - Addressing1/14/2019 1/14/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS1/14/2019 1/14/2019 PASS
DetailsMorgan Webb
Application received  1/11/2019 DONE
Application submitted via PDS Online on Jan 11 2019 10:09AM