Information based on query as of Monday, May 20, 2024.
Permit Information
Permit NumberBLD19-00264
StatusIssued
Name PARKLANE MANAGEMENT COMPANY LLC
Site Address 718 W IDAHO ST
Project NameUnion Block Basement Renovatio
Customer Number 
ePlanReviewYes
Description
(UNION BLOCK BASEMENT) **NO OCCUPANCY ALLOWED UNDER THIS PERMIT. TENANT SHALL APPLY FOR CERTIFICATE OF OCCUPANCY PRIOR TO OCCUPYING THE SPACE. ** The fire sprinkler system is used for story and area increase. To remodel the entire basement level and lower the basement floor 3’ to increase ceiling height for basement tenants. The existing basement has a ceiling height of 7’ and will be increased to an approximate ceiling height of 10’. Work in the basement is about 14,270 square feet and includes removing the existing slab, providing new support at interior structural walls, columns, and east/west exterior walls and providing a new floor slab. The light wells have been permitted under BLD18-01664. SPECIAL INSPECTIONS are required for fabrication, structural steel, concrete, post-installed concrete anchors, soils, and welding. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. The fire alarm system needs to be maintained because the B Occupancy occupant load of the 2nd story exceeds 100. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **JHB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Footing3/30/20203/31/20203/31/2020APEND
DetailsDave Hannah
in the alley behind // annie Phone #: ###-#### ok after spec inspection sign offs
BLD-Aging Inspection3/5/20203/5/20203/9/2020 PEND
DetailsDave Hannah
BLD-Aging Inspection3/4/20203/4/20203/9/2020 PEND
DetailsDave Hannah
BLD-Footing10/21/201910/22/201910/22/2019AFAIL
DetailsDave Hannah
Annie- entrace to work area in thru the Alley Phone #: ###-#### needs spec.inspection
BLD-Footing9/25/20199/25/20199/25/2019PPART
DetailsJim Storey
Anne Phone #: ###-#### rebar ok 4 locations/ vert at one ok to place wall.
BLD-Footing8/15/20198/16/20198/16/2019APART
DetailsDave Hannah
Annie Phone #: ###-#### first 6 ftgs ok
Issue PAID IN FULL permit  6/14/2019 DONE
Inspection Record Card- Bld  6/14/2019 DONE
Plan assigned to (JHB)5/9/20195/9/20196/13/2019 PASS
DetailsJoe Bruce
06/12 (3rd Rev) 05/31 (L3) Union Block Basement, ePlan
Routing Off Site - STRUCTURAL6/6/2019 6/13/2019 PASS
DetailsJoe Bruce
KPFF
PLANS/APPL TAKEN TO FRONT DESK  6/13/2019 DONE
Permit Ready to Issue  6/13/2019 DONE
ALL MET (lio@parklaneco.com)
Need GC
Need Rev Val
Plan resubmittals received  6/6/2019 DONE
DetailsJoe Bruce
Routing - PLAN CHECK6/6/2019 6/6/2019 PASS
DetailsJoe Bruce
Route to Impact Fee Review5/31/20196/3/20196/3/2019 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - FIRE5/9/20195/9/20195/31/2019 PASS
DetailsMark Scharfen
05/31 Completed fire review, uploaded rev_fire 05.31.2019.pdf.
Routing - PLAN CHECK5/9/2019 5/31/2019 FAIL
DetailsJoe Bruce
1st review completed  5/31/2019 FAIL
DetailsJoe Bruce
Routing Off Site - STRUCTURAL5/9/2019 5/24/2019 FAIL
DetailsJoe Bruce
KPFF - Corrections Required, see ePlan changemarks.
Routing - Design Review5/9/2019 5/13/2019 PASS
DetailsJosh Wilson
Ok for basement work only. Condiitons for exterior work have not been met.
Routing - PLANNING5/9/2019 5/10/2019 PASS
DetailsDavid Moser
See DRH17-00571
Routing - Erosion and Sediment5/9/2019 5/10/2019 PASS
DetailsAndy J. Long
project may be covered under existing permit, ESC18-00778. No new ESC permit required.
Routing - Addressing5/9/2019 5/9/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS5/9/2019 5/9/2019 PASS
DetailsAngela Hardy
Intake Approval  5/6/2019 PASS
Intake Approval  1/25/2019 FAIL
DetailsJoe Bruce
1. Provide a COMPLETE soils report that is stamped and signed by an Idaho licensed engineer for the soil bearing pressure stated on the structural drawings. The soils report submitted was incomplete and shall comply with IBC section 1803.6.
2. Plan sheet, S3.1 does not have the required space reserved for City approval stamps as specified in the Electronic Plans Submittal Standards. Revise sheet with a blank 4” x 2” located 3” off the right sheet edge to allow for the title block. Verify ALL plan sheets have the required space for city approval stamp.
Application received  1/23/2019 DONE
Application submitted via PDS Online on Jan 23 2019 5:33PM