BLD-Aging Inspection | 8/14/2019 | 8/14/2019 | 8/15/2019 | | PASS |
Jim Storey
|
|
|
nr/ pending mech
|
BLD-Energy code compliance | 4/1/2019 | 4/1/2019 | 4/1/2019 | P | PASS |
Jim Storey
|
|
|
Eric Phone #: ###-####
|
BLD-Framing/Rough-in | 3/29/2019 | 3/29/2019 | 3/29/2019 | P | PART |
Tony Young
|
|
|
Eric Phone #: ###-####,, needs a mechanical permit,, ok to insulate only,, ok to cover exterior
|
BLD-Final | 3/28/2019 | 3/29/2019 | 3/29/2019 | P | NR |
Tony Young
|
|
|
Eric Phone #: ###-####,, wanted a frame inspection
|
Plan assigned to (JAB) Josh | 3/12/2019 | 3/12/2019 | 3/12/2019 | | PASS |
Josh Bogle
|
|
|
|
Routing Walk-In (Zoning) | 3/12/2019 | 3/12/2019 | 3/12/2019 | P | DONE |
Colleen T Carroll
|
|
|
east/west patio cover only. previous work approved on Febraury 5, 2019
|
Routing Walk-In (BLD) | 3/12/2019 | 3/12/2019 | 3/12/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 3/12/2019 | | 3/12/2019 | | PASS |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 3/12/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 3/12/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 3/12/2019 | | DONE |
|
|
|
plan mod
|
Plan Modification Accepted | | | 3/12/2019 | | DONE |
|
|
|
plan mod-changes are going to be to the patio-assigned to JAB
|
BLD-Footing | 2/12/2019 | 2/12/2019 | 2/12/2019 | P | PASS |
Jim Storey
|
|
|
Eric Phone #: ###-####
|
Routing Walk-In (BLD) | 2/5/2019 | 2/5/2019 | 2/5/2019 | A | FAIL |
Josh Bogle
|
|
|
plans lacked required details
|
Routing Walk-In (BLD) | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 2/5/2019 | | 2/5/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 2/5/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 2/5/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 2/5/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/5/2019 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 1/31/2019 | 1/31/2019 | 1/31/2019 | P | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 1/31/2019 | 1/31/2019 | 1/31/2019 | P | FAIL |
Rob Patrick
|
|
|
Needs rescheck and more detail of construction
|
1st review completed | | | 1/31/2019 | | DONE |
Josh Bogle
|
|
|
|
Application received | | 1/31/2019 | | | |
|
|
|
|