Second Notice | | 8/15/2019 | 9/18/2019 | | DONE |
|
|
|
mailed 9-19-19
|
First Notice | | 7/26/2019 | 8/5/2019 | | DONE |
|
|
|
mailed 8-5-2019
|
BLD-Final | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | PASS |
Dave Hannah
|
|
|
Taylor Phone #: ###-####
|
FIRE-Final Inspection | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, hood suppression system inspection is complete, fire extinguishers are placed, including Class K extinguisher and all have current inspection tags. Final life fire safety inspection for area of work complete.
Taylor Phone #: ###-####
|
Permanent Occupancy | | | 7/16/2019 | | DONE |
|
|
|
|
Zoning Approval | 7/12/2019 | 7/12/2019 | 7/12/2019 | | DONE |
Andrea Tuning
|
|
|
|
FIRE-Conference | 7/11/2019 | 7/11/2019 | 7/11/2019 | P | DONE |
Jim Page
|
|
|
Fire conference complete.
Taylor Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 6/28/2019 | 7/1/2019 | 7/1/2019 | A | PASS |
Dave Hannah
|
|
|
Taylor Phone #: ###-####
|
Plan assigned to (JHB) | 6/26/2019 | 6/26/2019 | 6/28/2019 | | PASS |
Joe Bruce
|
|
|
(plan mod) A-Cafe
|
Routing - PLAN CHECK | 6/28/2019 | | 6/28/2019 | | PASS |
Joe Bruce
|
|
|
Mechanical ductwork modified as inspected in field by Chad Schwendiman. **JHB**
|
Permit Ready to Issue | | | 6/28/2019 | | DONE |
|
|
|
DO NOT ISSUE-plan mod
|
CHANGE STATUS TO (ISS) | | | 6/28/2019 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 6/26/2019 | | DONE |
|
|
|
close a mechanical damper
|
BLD-Ceiling Grid Inspection | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | CANC |
Dave Hannah
|
|
|
Taylor Phone #: ###-####
|
BLD-Framing/Rough-in | 5/28/2019 | 5/28/2019 | 5/28/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 5/24/2019 | 5/28/2019 | 5/28/2019 | A | DONE |
Dave Hannah
|
|
|
Taylor Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 4/25/2019 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 3/21/2019 | 3/21/2019 | 4/24/2019 | | PASS |
Joe Bruce
|
|
|
04/23 (2nd Rev) 04/15 (L3) A-Cafe Level 3 ePlan (Plan Check, Struc)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/24/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/24/2019 | | DONE |
|
|
|
ALL MET-
NEED
GC FORM
REVISED VALUE
|
Issue PAID IN FULL permit | | | 4/24/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/24/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 4/24/2019 | | DONE |
|
|
|
Waiting for Sewer fees to be paid,- Change status to issued when sewer fees are paid and release plans in eplan
|
Routing Off Site - STRUCTURAL | 4/17/2019 | | 4/23/2019 | | PASS |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 4/17/2019 | | 4/22/2019 | | PASS |
Joe Bruce
|
|
|
|
Plan resubmittals received | | | 4/17/2019 | | DONE |
Joe Bruce
|
|
|
|
Route to Impact Fee Review | 4/15/2019 | 4/18/2019 | 4/16/2019 | | PASS |
Karina Myles
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 3/21/2019 | 3/21/2019 | 4/15/2019 | | PASS |
Mark Scharfen
|
|
|
IFC Review 04.15.2019.pdf
|
1st review completed | | | 4/15/2019 | | DONE |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 4/15/2019 | | DONE |
Joe Bruce
|
|
|
|
Routing - PLAN CHECK | 3/21/2019 | | 4/11/2019 | | FAIL |
Joe Bruce
|
|
|
|
Routing Off Site - STRUCTURAL | 3/21/2019 | | 4/3/2019 | | FAIL |
Joe Bruce
|
|
|
|
Routing - MECHANICAL | 3/21/2019 | | 3/26/2019 | | PASS |
Troy James
|
|
|
|
Routing PW Environmental | 3/21/2019 | | 3/25/2019 | | PASS |
Terry Alber
|
|
|
Based on on-site inspection, grease abatement is available. Size of grease interceptor may or may not be adequate for all facilities in building. Peak flow rate of all connected facilities shall not exceed manufacturer's rating.
|
Intake Approval | | | 3/21/2019 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
pre screen accepted by M_H
|
Routing PW Solid Waste | 3/21/2019 | | 3/21/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing - PLUMBING | 3/21/2019 | | 3/21/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 3/21/2019 | | 3/21/2019 | | PASS |
Doug Chausow
|
|
|
Corrected address: 109 S 10th St
|
Routing - PUBLIC WORKS | 3/21/2019 | | 3/21/2019 | | PASS |
Angela Hardy
|
|
|
|
Routing - Erosion and Sediment | 3/21/2019 | | 3/21/2019 | | PASS |
Michael Zawacki
|
|
|
Minor TI, no disturbance, no ESC required.
|
Routing - Design Review | 3/21/2019 | | 3/21/2019 | | PASS |
KayCee Babb
|
|
|
Per DRH19-00059 and rooftop mechanical equipment approved through DRH19-00080.
|
Intake Approval | | | 3/1/2019 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. Provide structural calculations demonstrating sufficient structural capacity for the new mechanical equipment on the roof.
|
Application received | | | 2/22/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 22 2019 1:13PM
|